A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started.

What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?

A.
Load the project template once the team has bandwidth to start on the project.
Answers
A.
Load the project template once the team has bandwidth to start on the project.
B.
Create projects but leave the roles in place without assigning users.
Answers
B.
Create projects but leave the roles in place without assigning users.
C.
Create a custom status for Backlog to use prior to using the Planning status.
Answers
C.
Create a custom status for Backlog to use prior to using the Planning status.
Suggested answer: C

Explanation:

In Workfront, creating a custom status specifically for 'Backlog' allows the team to differentiate between work that is pending capacity and work that is actively being planned. This prevents confusion and allows for better project tracking, ensuring that tasks move smoothly from backlog to the planning phase when appropriate.