What item, when shared with a user, can never give that user inherited permission to a project?

A.
Portfolio
A.
Portfolio
Answers
B.
Task
B.
Task
Answers
C.
Report
C.
Report
Answers
Suggested answer: C

Explanation:

Adobe Workfront, permissions can be inherited through various objects like projects, portfolios, or tasks when shared with users. However, when sharing a report, the permissions do not cascade to related items like projects or tasks within that report. This is because reports are generated views and do not directly control object-level permissions. A report can be shared to allow a user to see data within the report, but it will not grant them inherited permissions to the underlying projects or tasks displayed in that report.

What parent object can have child objects?

A.
Issue
A.
Issue
Answers
B.
Project
B.
Project
Answers
C.
Portfolio
C.
Portfolio
Answers
Suggested answer: C

Explanation:

In Workfront, a 'Portfolio' is a parent object that can contain multiple programs and projects. Each Portfolio can have a hierarchy of child objects such as programs, which further break down into projects. A project, while it contains tasks and issues, is considered a child within the larger hierarchy of a portfolio. Issues, on the other hand, are typically linked to tasks or projects but are not used as parent objects. This hierarchy enables Workfront users to organize and manage their work across various levels.

Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.

Why may this be the case?

A.
The primary task owner has time off logged in Workfront.
A.
The primary task owner has time off logged in Workfront.
Answers
B.
The team needs to review the task before confirming the start date.
B.
The team needs to review the task before confirming the start date.
Answers
C.
The task duration and planned hours are set to begin on Friday.
C.
The task duration and planned hours are set to begin on Friday.
Answers
Suggested answer: C

Explanation:

In Workfront, tasks are governed by several factors such as task duration, planned hours, and predecessors. In this case, the most likely reason for the task starting later than expected is due to the task's duration and planned hours being configured to start on Friday. Even though the predecessor may suggest an earlier start, task settings such as constraints and assigned hours can override the default scheduling. Additionally, task constraints, like 'Fixed Start' or 'Fixed Finish,' can influence when tasks appear on the schedule.

A project manager has set up and launched a new project for an annual marketing campaign.

Where can the project team locate their work requests?

A.
Email, Workfront Home, Project tasks list
A.
Email, Workfront Home, Project tasks list
Answers
B.
Email, Automatic Reminders, Workfront Home
B.
Email, Automatic Reminders, Workfront Home
Answers
C.
Event Notifications, Approval processes, Email
C.
Event Notifications, Approval processes, Email
Answers
Suggested answer: A

Explanation:

Workfront provides multiple ways for team members to track and locate their assigned work. The primary tools include the Workfront Home area, which centralizes all work items assigned to a user, and email notifications that can alert users to new assignments or updates. Additionally, users can view specific tasks in the Project tasks list. Workfront Home is a key component for workers as it consolidates all active assignments and updates in a single view.

A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.

How should the project manager keep these team members apprised of updates?

A.
Subscribe the team members to the request.
A.
Subscribe the team members to the request.
Answers
B.
Ask the team members to add the request to their favorites.
B.
Ask the team members to add the request to their favorites.
Answers
C.
Make the team members all primary contacts on the request.
C.
Make the team members all primary contacts on the request.
Answers
Suggested answer: A

Explanation:

In Adobe Workfront, team members can be subscribed to a request so that they receive updates whenever changes or comments are made. This ensures they stay informed of any progress or issues. Adding a request to favorites only bookmarks it for easy access, but does not trigger automatic notifications. Making multiple primary contacts is not an efficient way to handle notifications.

A system administrator has created a Marketing Request Queue that routes to the marketing team. This team needs to manage various incoming requests from the organization through emails, instant messaging, and conversations. Team members receive request notifications in their emails but are still having difficulties monitoring and prioritizing incoming requests.

Which reports would be helpful to have on a dashboard for the marketing team to manage incoming work requests?

A.
Four reports showing the entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, a third report that shows recently completed requests, and a fourth report that shows the schedule assigned to each team member.
A.
Four reports showing the entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, a third report that shows recently completed requests, and a fourth report that shows the schedule assigned to each team member.
Answers
B.
Two reports showing the priority and actual completion date of each request, i.e., one that shows active requests and another that shows recently completed requests.
B.
Two reports showing the priority and actual completion date of each request, i.e., one that shows active requests and another that shows recently completed requests.
Answers
C.
Three reports showing the priority and entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, and one that shows recently completed requests.
C.
Three reports showing the priority and entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, and one that shows recently completed requests.
Answers
Suggested answer: C

Explanation:

To help the marketing team manage incoming work requests, the most effective reports would focus on the priority and entry date of requests. These reports would allow the team to quickly view what requests are new, in progress, or completed, enabling them to prioritize work accordingly. A report that tracks the 'entry date' helps in monitoring how long a request has been waiting, while status-based reports help in identifying the current stage of each request.

How is the primary assignee of a task determined?

A.
By the user on a task that has a primary job role.
A.
By the user on a task that has a primary job role.
Answers
B.
By the Home Team assigned to a task.
B.
By the Home Team assigned to a task.
Answers
C.
By the user that is assigned first to a task.
C.
By the user that is assigned first to a task.
Answers
Suggested answer: C

Explanation:

In Adobe Workfront, when multiple users are assigned to a task, the system designates the user who was assigned first as the primary assignee. This is the user responsible for driving the task to completion, and their name will appear in the primary assignee field. This approach ensures clear accountability within teams.

A project manager is assigned to a new Workfront request. The request specifies that the management team's sign-off is needed before the project can begin.

What is the appropriate action for the project manager to take?

A.
Convert the issue into a project using a project template.
A.
Convert the issue into a project using a project template.
Answers
B.
Email the management team and request their approval.
B.
Email the management team and request their approval.
Answers
C.
Use a customized approval process to route the issue for approval.
C.
Use a customized approval process to route the issue for approval.
Answers
Suggested answer: C

Explanation:

In Workfront, approval processes are designed to handle scenarios where certain team members must give formal approval before work can proceed. In this case, the project manager should set up a customized approval process that routes the request through the necessary stakeholders (management team) for their sign-off. This ensures proper governance and tracking.

A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.

Which action should the stakeholder take to log the risk?

A.
Log a risk as part of the project business case and identify it as a 'schedule' risk.
A.
Log a risk as part of the project business case and identify it as a 'schedule' risk.
Answers
B.
Log an issue on the project and explain that the completion date is at risk.
B.
Log an issue on the project and explain that the completion date is at risk.
Answers
C.
Create a task in the project and set the Planned Completion Date for 2 weeks.
C.
Create a task in the project and set the Planned Completion Date for 2 weeks.
Answers
Suggested answer: A

Explanation:

In Adobe Workfront, risks associated with a project should be logged as part of the project business case. The 'Risk' section within the business case allows stakeholders to document any potential threats to the project timeline, scope, or resources. Identifying this risk as a 'schedule' risk helps communicate the potential delay to the project stakeholders and allows it to be tracked and mitigated effectively.

A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.

What impact does this have on the project progress status?

A.
The next team member cannot start his task.
A.
The next team member cannot start his task.
Answers
B.
No impact as the task is not overdue.
B.
No impact as the task is not overdue.
Answers
C.
The project shows an At Risk automatic condition.
C.
The project shows an At Risk automatic condition.
Answers
Suggested answer: C

Explanation:

In Workfront, if a task that is part of the critical path is delayed, it affects the overall project schedule. Even though the task is not overdue yet, Workfront's automated system flags the project as 'At Risk' if there is a delay in progress that could impact the project's timeline. This 'At Risk' condition acts as a warning to project managers and stakeholders that immediate attention is needed.

Total 70 questions