A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.

What steps should the project manager take to create a custom Workfront report with this information?

A.
Visit the Reports page, create a new Project report, and add filters for Company ID and Group ID.
A.
Visit the Reports page, create a new Project report, and add filters for Company ID and Group ID.
Answers
B.
Visit the Reports page, create a new Project report, and add filters for Company ID and Owner ID.
B.
Visit the Reports page, create a new Project report, and add filters for Company ID and Owner ID.
Answers
C.
Visit the Reports page, create a new Project report, and add filters for Owner ID and Project Status.
C.
Visit the Reports page, create a new Project report, and add filters for Owner ID and Project Status.
Answers
Suggested answer: A

Explanation:

To provide a list of all projects for a specific company (Acme) and group (Marketing), the correct approach is to filter by both Company ID and Group ID in the custom project report. This allows the project manager to isolate projects related to Acme Company that the Marketing Group is responsible for.

To whom or what would a project owner assign a task so the task is visible in a Scrum or Kanban backlog?

A.
A user that has access to a burndown
A.
A user that has access to a burndown
Answers
B.
A job role labeled as Agile User
B.
A job role labeled as Agile User
Answers
C.
A team marked as an agile team
C.
A team marked as an agile team
Answers
Suggested answer: C

What occurs when an individual enters a new commit date that is after the original planned date of a task?

A.
The assignee of any task that has the original task set as a predecessor is notified.
A.
The assignee of any task that has the original task set as a predecessor is notified.
Answers
B.
The Project Owner is notified whether this change will impact the Project Timeline.
B.
The Project Owner is notified whether this change will impact the Project Timeline.
Answers
C.
The Planned Completion Date of the task automatically changes to match the new Commit Date.
C.
The Planned Completion Date of the task automatically changes to match the new Commit Date.
Answers
Suggested answer: C

Explanation:

When a user updates the Commit Date to a date later than the original planned date in Adobe Workfront, the Planned Completion Date of the task is automatically updated to reflect the new commit date. This feature ensures that the timeline is adjusted based on the most current commitment by the task assignee, which can then impact downstream tasks and the overall project schedule.

This change streamlines project planning and helps keep task dependencies aligned with realistic completion expectations.

A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?

A.
Utilization section
A.
Utilization section
Answers
B.
Hours tab
B.
Hours tab
Answers
C.
Finance section
C.
Finance section
Answers
Suggested answer: C

Explanation:

To view the Budgeted Variances between the planned and actual hours for the current week, the project manager should navigate to the Finance section of the project. This section provides detailed financial information, including cost and hour variances, which help track how actual project performance compares to the initial budget and plan. The Hours tab typically displays the logged hours, while the Utilization section is more focused on resource usage and allocation.

Which date type on tasks can a project manager manually modify?

A.
Planned
A.
Planned
Answers
B.
Estimated
B.
Estimated
Answers
C.
Projected
C.
Projected
Answers
Suggested answer: A

Explanation:

In Adobe Workfront, Planned Dates are the dates that project managers can manually modify. These dates represent the schedule that the project is expected to follow and can be adjusted based on project needs. Estimated and Projected Dates are automatically calculated by the system based on task progress and dependencies, and these cannot be manually modified directly by a project manager. The Projected date is influenced by changes in the actual completion rate of tasks, whereas the Planned Date is the baseline schedule.

Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?

A.
Status
A.
Status
Answers
B.
Condition
B.
Condition
Answers
C.
Progress Status
C.
Progress Status
Answers
Suggested answer: B

Explanation:

In Adobe Workfront, Condition is the reportable variable that is determined by the relationship between the Planned, Projected, and Estimated Dates. The Condition field reflects whether a project is On Target, At Risk, or In Trouble based on how its actual progress aligns with the planned schedule and dates. It allows project managers and stakeholders to quickly assess the health of the project.

Which date type should an assignee update to change the completion date of a task?

A.
Actual Completion Date
A.
Actual Completion Date
Answers
B.
Commit Date
B.
Commit Date
Answers
C.
Planned Completion Date
C.
Planned Completion Date
Answers
D.
Projected Start Date
D.
Projected Start Date
Answers
Suggested answer: C

Explanation:

In Workfront, to update the planned completion of a task, the assignee should modify the 'Planned Completion Date.' This date is used for scheduling and planning purposes to track when the task is expected to be finished. Changing the 'Planned Completion Date' adjusts the task's projected timeline and allows for a recalculation of project dependencies.

A company expects managers to complete a Workfront Business Case and submit it to the Project Sponsor for approval before a project enters Planning status.

What Workfront process will effectively facilitate the Project Sponsor review?

A.
Request Approval Process
A.
Request Approval Process
Answers
B.
Request Submission Process
B.
Request Submission Process
Answers
C.
Project Submission Process
C.
Project Submission Process
Answers
D.
Project Approval Process
D.
Project Approval Process
Answers
Suggested answer: B

Explanation:

In Workfront, the 'Request Submission Process' is used when a formal submission is required for review before the project proceeds to the planning phase. This process ensures that all necessary documentation, such as the business case, is completed and submitted to the sponsor for approval, streamlining the review process.

An IT department needs to see the Group and Portfolio of each of its projects for reporting purposes.

In which project area does this information reside?

A.
Queue Details
A.
Queue Details
Answers
B.
Project Details
B.
Project Details
Answers
C.
Metrics
C.
Metrics
Answers
Suggested answer: B

Explanation:

Adobe Workfront, information about the Group and Portfolio assigned to a project is stored in the 'Project Details' section. This section contains the overall information regarding a project, such as the Portfolio it belongs to and the Group responsible for it. The 'Queue Details' section pertains to request queues, while 'Metrics' generally involves the measurement and tracking of key performance indicators but not specific data like Group and Portfolio.

The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.

Which task settings should be configured to meet these requirements?

A.
The task Duration should be set to 2 days. A predecessor with a Finish-Start Dependency Type should be added to the second task with a lag of 5 days.
A.
The task Duration should be set to 2 days. A predecessor with a Finish-Start Dependency Type should be added to the second task with a lag of 5 days.
Answers
B.
Planned Hours should be set to 48 hours. A predecessor with a Finish-Start Dependency Type should be added to the first task with a lag of 5 days.
B.
Planned Hours should be set to 48 hours. A predecessor with a Finish-Start Dependency Type should be added to the first task with a lag of 5 days.
Answers
C.
The task Duration should be set to 48 hours. A predecessor with a Start-Finish Dependency Type should be added to the second task with a lag of 5 days.
C.
The task Duration should be set to 48 hours. A predecessor with a Start-Finish Dependency Type should be added to the second task with a lag of 5 days.
Answers
Suggested answer: A

Explanation:

In Adobe Workfront, to configure tasks according to the requirement of the second task beginning 5 business days after the first task, you need to set the appropriate 'Duration' and use 'Finish-Start' dependencies. The task's duration is key to determining the time allowed for its completion. The 'Finish-Start' dependency ensures that the second task begins only after the first is finished, and a lag can be set to introduce a delay, such as 5 business days. Setting a 'Finish-Start' dependency with a lag allows for proper scheduling of tasks in sequence without overlapping.

Total 70 questions