Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.

What may have caused the planned start date of Task 2 to remain the same?

The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.
The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.
The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.
The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.
The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.
The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.
The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.
The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.
Suggested answer: B

Explanation:

In this scenario, the fact that Task 2's start date did not shift automatically despite its dependency on Task 1 suggests that a manual override was applied, resulting in a Task Constraint of 'Must Start On.' This type of constraint locks a task to a specific date, preventing it from dynamically adjusting based on changes to its predecessor. The other options either do not explain why the start date remained static or involve user-specific scheduling conflicts, which would not affect the system-driven date adjustment.

asked 02/10/2024
Karsten Seifert
34 questions

Question 52

Report
Export
Collapse

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

Become a Premium Member for full access
  Unlock Premium Member

Question 53

Report
Export
Collapse

A marketing team determines that in the future, their projects must be reviewed by the Project Sponsor before the project is closed. What is the best practice to ensure that each project is properly reviewed and approved?

Become a Premium Member for full access
  Unlock Premium Member

Question 54

Report
Export
Collapse

What are two characteristics of a Group in Workfront? (Choose two.)

Become a Premium Member for full access
  Unlock Premium Member

Question 55

Report
Export
Collapse

Which two options are available with Workfront reports? (Choose two.)

Become a Premium Member for full access
  Unlock Premium Member

Question 56

Report
Export
Collapse

Refer to the exhibit.

Adobe AD0-E903 image Question 56 92419 10022024174913000000

Identified in red on a Gantt chart, what are the tasks called whose changes may affect the overall timeline of a project?

Become a Premium Member for full access
  Unlock Premium Member

Question 57

Report
Export
Collapse

Which field is used to create a milestone step on a milestone path in the Setup area?

Become a Premium Member for full access
  Unlock Premium Member

Question 58

Report
Export
Collapse

A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

Become a Premium Member for full access
  Unlock Premium Member

Question 59

Report
Export
Collapse

A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?

Become a Premium Member for full access
  Unlock Premium Member

Question 60

Report
Export
Collapse

Which project elements can be used to measure a project's adherence to its original schedule?

Become a Premium Member for full access
  Unlock Premium Member