Adobe AD0-E903 Practice Test - Questions Answers, Page 6
List of questions
Question 51
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.
What may have caused the planned start date of Task 2 to remain the same?
Explanation:
In this scenario, the fact that Task 2's start date did not shift automatically despite its dependency on Task 1 suggests that a manual override was applied, resulting in a Task Constraint of 'Must Start On.' This type of constraint locks a task to a specific date, preventing it from dynamically adjusting based on changes to its predecessor. The other options either do not explain why the start date remained static or involve user-specific scheduling conflicts, which would not affect the system-driven date adjustment.
Question 52
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?
Question 53
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A marketing team determines that in the future, their projects must be reviewed by the Project Sponsor before the project is closed. What is the best practice to ensure that each project is properly reviewed and approved?
Question 54
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
What are two characteristics of a Group in Workfront? (Choose two.)
Question 55
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which two options are available with Workfront reports? (Choose two.)
Question 56
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Refer to the exhibit.
Identified in red on a Gantt chart, what are the tasks called whose changes may affect the overall timeline of a project?
Question 57
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which field is used to create a milestone step on a milestone path in the Setup area?
Question 58
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?
Question 59
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?
Question 60
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which project elements can be used to measure a project's adherence to its original schedule?
Question