Adobe AD0-E903 Practice Test - Questions Answers, Page 6

Question list
Search
Search

List of questions

Search

Related questions











Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.

What may have caused the planned start date of Task 2 to remain the same?

A.
The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.
A.
The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.
Answers
B.
The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.
B.
The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.
Answers
C.
The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.
C.
The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.
Answers
D.
The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.
D.
The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.
Answers
Suggested answer: B

Explanation:

In this scenario, the fact that Task 2's start date did not shift automatically despite its dependency on Task 1 suggests that a manual override was applied, resulting in a Task Constraint of 'Must Start On.' This type of constraint locks a task to a specific date, preventing it from dynamically adjusting based on changes to its predecessor. The other options either do not explain why the start date remained static or involve user-specific scheduling conflicts, which would not affect the system-driven date adjustment.

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

A.
Projected Date
A.
Projected Date
Answers
B.
Planned Date
B.
Planned Date
Answers
C.
Estimated Date
C.
Estimated Date
Answers
Suggested answer: A

Explanation:

The Projected Date in Adobe Workfront is dynamically calculated based on the progress of the task, any task constraints, and its dependencies. This date provides a more accurate reflection of when a task is likely to be completed, considering the current progress and any updates to predecessor tasks. On the other hand, the Planned Date refers to the originally scheduled completion date, and the Estimated Date is not manually entered but inferred from system calculations.

A marketing team determines that in the future, their projects must be reviewed by the Project Sponsor before the project is closed. What is the best practice to ensure that each project is properly reviewed and approved?

A.
Create a new approval process in the global setup area that will ensure that an approval process is attached to all Marketing Projects.
A.
Create a new approval process in the global setup area that will ensure that an approval process is attached to all Marketing Projects.
Answers
B.
Create a single-use approval process on each project that routes to the Project Sponsor for approval once the project status is set to Complete.
B.
Create a single-use approval process on each project that routes to the Project Sponsor for approval once the project status is set to Complete.
Answers
C.
In the project template, add an approval process routing to the Project Sponsor for approval once the project status is set to Complete.
C.
In the project template, add an approval process routing to the Project Sponsor for approval once the project status is set to Complete.
Answers
Suggested answer: C

Explanation:

The best practice is to incorporate an approval process into the project template so that it is automatically triggered when a project reaches the completion stage. This ensures consistency and saves time by removing the need to manually set up approval processes for each new project. This approach also guarantees that the Project Sponsor's review is systematically included before the project is officially closed.

What are two characteristics of a Group in Workfront? (Choose two.)

A.
A Group can be tagged in an Update thread communication.
A.
A Group can be tagged in an Update thread communication.
Answers
B.
A Group assignment is not required for a user.
B.
A Group assignment is not required for a user.
Answers
C.
A Group can be associated with a Company or a Project.
C.
A Group can be associated with a Company or a Project.
Answers
D.
A user can be assigned as Group Administrator of a Group.
D.
A user can be assigned as Group Administrator of a Group.
Answers
Suggested answer: C, D

Explanation:

Groups in Adobe Workfront serve as organizational entities that can be associated with specific Companies or Projects to manage workflows or permissions more effectively. Additionally, each Group can have a Group Administrator assigned, who is responsible for managing the group's settings, permissions, and workflows. These roles and associations help in structuring how work and permissions are allocated across different teams or departments.

Which two options are available with Workfront reports? (Choose two.)

A.
A chart report that references a multi-select custom field
A.
A chart report that references a multi-select custom field
Answers
B.
Planned date-based calendar reports
B.
Planned date-based calendar reports
Answers
C.
Filters with a custom grouping
C.
Filters with a custom grouping
Answers
D.
An object name with more than 500 characters
D.
An object name with more than 500 characters
Answers
Suggested answer: B, C

Explanation:

In Adobe Workfront, Planned date-based calendar reports are commonly used to visualize project timelines, milestones, and deadlines. They help teams plan and manage workloads based on dates and other time-related factors.

Filters with custom grouping allow users to customize their reports by organizing data in a meaningful way, tailored to specific project or team requirements. Custom groupings enhance the clarity of reports by categorizing data based on selected criteria.

The other options are not correct because Workfront does not support reports that reference multi-select custom fields in a chart format, nor does it allow object names longer than 500 characters.

Refer to the exhibit.

Identified in red on a Gantt chart, what are the tasks called whose changes may affect the overall timeline of a project?

A.
Critical Path
A.
Critical Path
Answers
B.
Baselines
B.
Baselines
Answers
C.
Milestones
C.
Milestones
Answers
Suggested answer: A

Explanation:

In Adobe Workfront, and in general project management, the Critical Path refers to the sequence of tasks that directly impacts the project's overall timeline. Tasks on the critical path are marked in red on a Gantt chart to indicate that any delay or change to these tasks will affect the entire project's completion date. These tasks are essential for maintaining the project schedule and ensuring timely delivery. Baselines are used for comparison against the current progress, and Milestones mark significant checkpoints but do not necessarily affect the project timeline if they are delayed.

Which field is used to create a milestone step on a milestone path in the Setup area?

A.
Status
A.
Status
Answers
B.
Description
B.
Description
Answers
C.
Key
C.
Key
Answers
Suggested answer: C

Explanation:

In Adobe Workfront, when creating a Milestone Step within the Setup area, the Key field is essential as it serves as a unique identifier for each milestone step. It is used to define the specific step within a milestone path that can be associated with tasks in a project. The Status and Description fields are not used for creating the milestone step itself but are more relevant for defining attributes or metadata.

A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

A.
Actual Completion Date
A.
Actual Completion Date
Answers
B.
Progress Status
B.
Progress Status
Answers
C.
Status
C.
Status
Answers
Suggested answer: C

Explanation:

Even though tasks may be marked as 100% complete, their Status may still be listed as incomplete in reports if the task's status has not been updated to 'Completed.' The Status column provides insight into the current state of the task, which helps identify if the task is still listed as 'In Progress' or another incomplete status despite being marked as fully complete. Adding this column clarifies why the task appears in the Incomplete Tasks Report.

A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?

A.
Visit the Reports page and create a Project report. In the filter, update the actual completion date value to 'past year' and update the Project Sponsor ID field to the project sponsor's name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select 'month.'
A.
Visit the Reports page and create a Project report. In the filter, update the actual completion date value to 'past year' and update the Project Sponsor ID field to the project sponsor's name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select 'month.'
Answers
B.
Visit the Reports page and create a Project Sponsor report. In the filter, update the actual completion date value with custom dates for the past year and update the Project Sponsor ID field to the project sponsor's name. In the grouping tab, add a grouping for the planned completion date. In the Group Dates by field, select 'month of year.'
B.
Visit the Reports page and create a Project Sponsor report. In the filter, update the actual completion date value with custom dates for the past year and update the Project Sponsor ID field to the project sponsor's name. In the grouping tab, add a grouping for the planned completion date. In the Group Dates by field, select 'month of year.'
Answers
C.
Visit the Dashboards page and create a Project report. In the filter, update the actual completion date value to 'past year' and update the Project Sponsor ID field to the project sponsor's name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select 'month of year.'
C.
Visit the Dashboards page and create a Project report. In the filter, update the actual completion date value to 'past year' and update the Project Sponsor ID field to the project sponsor's name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select 'month of year.'
Answers
Suggested answer: A

Explanation:

The best approach is to generate a Project Report in Workfront, where the report filters the Actual Completion Date for the past year and groups projects by the Sponsor and the month of completion. This allows the sponsor to see exactly which projects they sponsored and when they were completed within the selected timeframe. Grouping by month provides a clear visual of the completion timeline.

Which project elements can be used to measure a project's adherence to its original schedule?

A.
Number of tasks, actual completion dates, and project status
A.
Number of tasks, actual completion dates, and project status
Answers
B.
Project baselines, planned completion dates, and actual completion dates
B.
Project baselines, planned completion dates, and actual completion dates
Answers
C.
Workload balancer data, planned completion dates, and expenses
C.
Workload balancer data, planned completion dates, and expenses
Answers
Suggested answer: B

Explanation:

To measure a project's adherence to its original schedule, the most critical elements are Project Baselines, Planned Completion Dates, and Actual Completion Dates. The baseline captures the original planned schedule, while the planned and actual completion dates provide the data to compare the project's progress against the initial schedule. This comparison helps project managers identify any deviations from the original plan and assess the project's performance.

Total 70 questions