A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.

Which date type would the project manager utilize?

A.
Estimated Date
Answers
A.
Estimated Date
B.
Projected Date
Answers
B.
Projected Date
C.
Planned Date
Answers
C.
Planned Date
Suggested answer: B

Explanation:

The 'Projected Date' in Workfront reflects the most likely completion date of a task based on the task's progress and any predecessors. Unlike the 'Planned Date,' which is set manually, the Projected Date automatically updates as task progress changes, giving a real-time estimate of task completion.