Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.

Why may this be the case?

A.
The primary task owner has time off logged in Workfront.
Answers
A.
The primary task owner has time off logged in Workfront.
B.
The team needs to review the task before confirming the start date.
Answers
B.
The team needs to review the task before confirming the start date.
C.
The task duration and planned hours are set to begin on Friday.
Answers
C.
The task duration and planned hours are set to begin on Friday.
Suggested answer: C

Explanation:

In Workfront, tasks are governed by several factors such as task duration, planned hours, and predecessors. In this case, the most likely reason for the task starting later than expected is due to the task's duration and planned hours being configured to start on Friday. Even though the predecessor may suggest an earlier start, task settings such as constraints and assigned hours can override the default scheduling. Additionally, task constraints, like 'Fixed Start' or 'Fixed Finish,' can influence when tasks appear on the schedule.