Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

A.
Projected Date
Answers
A.
Projected Date
B.
Planned Date
Answers
B.
Planned Date
C.
Estimated Date
Answers
C.
Estimated Date
Suggested answer: A

Explanation:

The Projected Date in Adobe Workfront is dynamically calculated based on the progress of the task, any task constraints, and its dependencies. This date provides a more accurate reflection of when a task is likely to be completed, considering the current progress and any updates to predecessor tasks. On the other hand, the Planned Date refers to the originally scheduled completion date, and the Estimated Date is not manually entered but inferred from system calculations.

asked 02/10/2024
Alain Bijl
40 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first