ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 58 - AD0-E903 discussion

Report
Export

A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

A.
Actual Completion Date
Answers
A.
Actual Completion Date
B.
Progress Status
Answers
B.
Progress Status
C.
Status
Answers
C.
Status
Suggested answer: C

Explanation:

Even though tasks may be marked as 100% complete, their Status may still be listed as incomplete in reports if the task's status has not been updated to 'Completed.' The Status column provides insight into the current state of the task, which helps identify if the task is still listed as 'In Progress' or another incomplete status despite being marked as fully complete. Adding this column clarifies why the task appears in the Incomplete Tasks Report.

asked 02/10/2024
Website Subscription
37 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first