Which project elements can be used to measure a project's adherence to its original schedule?

A.
Number of tasks, actual completion dates, and project status
Answers
A.
Number of tasks, actual completion dates, and project status
B.
Project baselines, planned completion dates, and actual completion dates
Answers
B.
Project baselines, planned completion dates, and actual completion dates
C.
Workload balancer data, planned completion dates, and expenses
Answers
C.
Workload balancer data, planned completion dates, and expenses
Suggested answer: B

Explanation:

To measure a project's adherence to its original schedule, the most critical elements are Project Baselines, Planned Completion Dates, and Actual Completion Dates. The baseline captures the original planned schedule, while the planned and actual completion dates provide the data to compare the project's progress against the initial schedule. This comparison helps project managers identify any deviations from the original plan and assess the project's performance.