Question 34 - AD0-E908 discussion
Refer to the exhibit.
Tyson has a capacity of 7 hours per day.
What two changes can the system administrator make to this user's workload from within the Workload Balancer to ensure that they are not overallocated? (Choose two.)
A.
Edit the allocation of the 'Verify Intake Form' task to migrate hours from Wednesday to another day
B.
Change the planned completion date of the 'Kickoff Meeting' task to another day of the week
C.
Reassign the 'Kickoff Meeting' task to another user who is not over-allocated
D.
Change the status of the 'Kickoff Meeting' task to cancelled to remove the hours from the user's allocation