A marketing team is trying to create a new project template for a repeatable workflow. They need to capture phases within each project and ensure tasks support critical-path timelines.

Which two items need to be completed for the efficient use of a project template? (Choose two.)

A.
Predecessors
Answers
A.
Predecessors
B.
Job Roles
Answers
B.
Job Roles
C.
Task Planned Hours
Answers
C.
Task Planned Hours
D.
Milestone Tasks
Answers
D.
Milestone Tasks
Suggested answer: A, D

Explanation:

For efficient use of a project template that captures phases within each project and supports critical-path timelines, the following elements are essential:

Predecessors: These define the relationships between tasks, ensuring that the sequence of tasks reflects their dependencies. This is crucial for maintaining the integrity of the critical path.

Milestone Tasks: These are key tasks that mark significant points or stages in the project timeline. Including milestone tasks helps in tracking progress and ensuring that critical deadlines are met.

Reference

The importance of predecessors and milestone tasks in project templates is emphasized in Workfront's project management guidelines and best practices for creating reusable workflows.