Question 11

Report Export Collapse

What does the Cost Performance Index (CPI) of a project in Workfront track?

Relationship between the planned and actual cost
Relationship between the planned and actual cost
Difference between the planned benefit and budgeted cost
Difference between the planned benefit and budgeted cost
Total expected value after calculating its benefit and removing the costs
Total expected value after calculating its benefit and removing the costs
Suggested answer: A
Explanation:

The CPI measures the cost efficiency of budgeted resources on a project. It is calculated by dividing the earned value (EV) by the actual cost (AC). A CPI value greater than 1 indicates that the project is under budget.

asked 02/10/2024
Morten Sivertsen
33 questions

Question 12

Report Export Collapse

A designer notices that no tasks associated with a specific project appear on their timesheet. The project owner verified that the designer is assigned to several tasks and that the tasks occur during the week of the current timesheet

Which setting can cause this experience?

Task assignees must be given contribute access to a project in order for the tasks to automatically appear
Task assignees must be given contribute access to a project in order for the tasks to automatically appear
A projects status must equate to Current in order for its tasks and issues to automatically appear on timesheets.
A projects status must equate to Current in order for its tasks and issues to automatically appear on timesheets.
All predecessors for a tasks must be complete before they will appear on a timesheet
All predecessors for a tasks must be complete before they will appear on a timesheet
Suggested answer: B
Explanation:

Project status and timesheets:

For tasks to appear on a timesheet, the project status must be set to 'Current.' If the project status is anything other than Current (e.g., Planning, Complete, or On Hold), tasks from that project will not automatically populate the timesheet.

asked 02/10/2024
Ioana Mihaila
53 questions

Question 13

Report Export Collapse

An administrator has assigned custom project status names to the Finance group. The administrator creates a sub-group under the Finance group, called 'AP\

Which project status names will apply to the AP sub-group?

The default names assigned to the Workfront instance
The default names assigned to the Workfront instance
The same names as the Finance group
The same names as the Finance group
The default Workfront status names
The default Workfront status names
Suggested answer: B
Explanation:

Inherited status names:

Sub-groups inherit the project status names from their parent group unless explicitly overridden. Therefore, the AP sub-group under the Finance group will use the same custom project status names assigned to the Finance group.

asked 02/10/2024
Wilson Geneblazo
36 questions

Question 14

Report Export Collapse

Which two objects can an issue be converted to? (Choose two.)

Become a Premium Member for full access
  Unlock Premium Member

Question 15

Report Export Collapse

What is the hierarchical relationship between a Queue Topic and Topic Group?

Become a Premium Member for full access
  Unlock Premium Member

Question 16

Report Export Collapse

A project manager needs to share a Custom Form that was created to support their portfolio. What should the project manager understand about this requirement?

Become a Premium Member for full access
  Unlock Premium Member

Question 17

Report Export Collapse

A Workfront developer is tasked with building a new custom form to collect project requests. The form will display different sets of options based on different selections, which requires the use of display logic and skip logic in the form.

What are two considerations the developer should take into account when building the conditional logic in the form? (Choose two.)

Become a Premium Member for full access
  Unlock Premium Member

Question 18

Report Export Collapse

In which scenario would an administrator use a request queue to resolve a business need?

Become a Premium Member for full access
  Unlock Premium Member

Question 19

Report Export Collapse

An organization wants to ensure that everyone can fill out the general project custom form associated with the general project template. What is the correct sharing setting for the custom form?

Become a Premium Member for full access
  Unlock Premium Member

Question 20

Report Export Collapse

A client wants to keep track of project metrics based on the request that was submitted, but they do not want the requestor to fill this information out. How would a system administrator configure this request?