An administrator has submitted a change request for an upcoming server deployment. Which of the following must be completed before the change can be approved?

A.
Risk analysis
Answers
A.
Risk analysis
B.
Sandbox testing
Answers
B.
Sandbox testing
C.
End user acceptance
Answers
C.
End user acceptance
D.
Lessons learned
Answers
D.
Lessons learned
Suggested answer: A

Explanation:

Risk analysis is the process of identifying and evaluating the potential threats and impacts of a change on the system, network, or service. It is an essential step before approving a change request, as it helps to determine the level of risk, the mitigation strategies, and the contingency plans.Risk analysis also helps to prioritize the change requests based on their urgency and importance12.