An administrator's change was approved by the change management review board. Which of the following should the administrator do next?

A.
Perform risk analysis.
Answers
A.
Perform risk analysis.
B.
Assign a change coordinator.
Answers
B.
Assign a change coordinator.
C.
Implement the change.
Answers
C.
Implement the change.
D.
Verify testing results.
Answers
D.
Verify testing results.
Suggested answer: C

Explanation:

Once a change has been approved by the change management review board, the next step is to:

Implement the change: This involves carrying out the approved change in the system or environment according to the change plan.

Perform risk analysis: This should be done before the change is approved to assess potential impacts.

Assign a change coordinator: This role should be designated earlier in the process to oversee the change implementation.

Verify testing results: This should have been done before seeking approval from the review board.

CompTIA A+ 220-1102 Exam Objectives, Section 4.2: Explain basic change-management best practices.

Change management process documentation.