ExamGecko
Home / Atlassian / ACP-610 / List of questions
Ask Question

Atlassian ACP-610 Practice Test - Questions Answers, Page 5

Add to Whishlist

List of questions

Question 41

Report Export Collapse

You just started working as a scrum master in the Engine team.

The first thing you do is to analyze the Velocity Chart of the team's scrum board as shown

Atlassian ACP-610 image Question 41 18243 09162024190126000000

Issues not completed in Combo Sprint 3 were completed in Combo Sprint 4.
Issues not completed in Combo Sprint 3 were completed in Combo Sprint 4.
Combo Sprint 1 has been deleted after it was completed.
Combo Sprint 1 has been deleted after it was completed.
There was a scope change during Combo Sprint 4.
There was a scope change during Combo Sprint 4.
The team only completed 2 out of 6 Story Points in Combo Sprint 3.
The team only completed 2 out of 6 Story Points in Combo Sprint 3.
All issues in Combo Sprint 3 were estimated before the sprint was started.
All issues in Combo Sprint 3 were estimated before the sprint was started.
Suggested answer: C
Explanation:

The Velocity Chart shows the amount of work completed by a team in each sprint. The green area represents the completed work, and the gray area represents the estimated work. The difference between the green and gray areas indicates a scope change, which means that issues were added or removed from the sprint after it started. In Combo Sprint 4, we can see that the green area is larger than the gray area, which means that more work was completed than estimated. This implies that some issues were added to the sprint after it started, or that some issues were re-estimated with higher values. Therefore, option C is correct.Reference:Velocity Chart,Managing Jira Projects Data Center and Server: Certification Bundle

asked 16/09/2024
Zaccheri Brown
37 questions

Question 42

Report Export Collapse

Development team A is consistently overestimating the work they can complete per sprint. They want to be able to compare work committed and work completed in sprints over time. Which single report provides this information?

Control Chart
Control Chart
Sprint Report
Sprint Report
Cumulative Flow Diagram
Cumulative Flow Diagram
Created vs Resolved Issues Report
Created vs Resolved Issues Report
Velocity Chart
Velocity Chart
Suggested answer: E
Explanation:

The Velocity Chart is the best report to compare work committed and work completed in sprints over time. It shows the average amount of work that a team can complete in a sprint, based on the historical data of previous sprints. It also shows how much work was planned and how much was actually completed in each sprint. By looking at the Velocity Chart, a team can see if they are overestimating or underestimating their capacity, and adjust their planning accordingly. Therefore, option E is correct.Reference:Velocity Chart,Managing Jira Projects Data Center and Server: Certification Bundle

asked 16/09/2024
Khalid Laghmami
30 questions

Question 43

Report Export Collapse

Your team has been completing work on a fully estimated epic in each of the last four sprints.

Your product owner wants you to predict how many additional sprints will be needed to complete it.

Which single report can provide the information?

Epic Burndown
Epic Burndown
Sprint Report
Sprint Report
Release Burndown
Release Burndown
Epic Report
Epic Report
Suggested answer: A
Explanation:

An epic burndown chart shows the progress towards completing an epic over time. It is useful for tracking how much work is left to be done and predicting when it will be completed. The epic burndown chart is based on the estimation statistic that is configured for the board (either story points or issue count) and shows the total amount of work remaining in the epic at the end of each sprint. You can use this chart to estimate how many additional sprints will be needed to complete an epic.Reference:: https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-epic-burndown-chart/

asked 16/09/2024
Wislon Pereira
41 questions

Question 44

Report Export Collapse

Paul and Tessa are in the Auditors role of every project.

You need to write a JQL query that shows Issues reported by either of them that are still unassigned.

Select the correct JQL query.

Reporter IN (Paul, Tessa) AND Assignee IS EMPTY
Reporter IN (Paul, Tessa) AND Assignee IS EMPTY
Reporter IN (Auditors) AND assignee - EMPTY
Reporter IN (Auditors) AND assignee - EMPTY
Reporter IN membersOfCAuditors') AND assignee = NULL
Reporter IN membersOfCAuditors') AND assignee = NULL
Reporter IS Paul OR Reporter IS Tessa AND Assignee IS NULL
Reporter IS Paul OR Reporter IS Tessa AND Assignee IS NULL
(Reporter - Paul OR Reporter -- Tessa) AND Assignee - Unassigned
(Reporter - Paul OR Reporter -- Tessa) AND Assignee - Unassigned
Suggested answer: A
Explanation:

The correct JQL query to find issues reported by either Paul or Tessa that are still unassigned is: Reporter IN (Paul, Tessa) AND Assignee IS EMPTY. This query uses the IN operator to specify a list of values for the Reporter field, and the IS EMPTY operator to check if the Assignee field has no value. The other options are incorrect because they use invalid syntax or operators, such as ''-'', NULL, or Unassigned. For more information on JQL syntax and operators, seeJQL operatorsandUse advanced search with Jira Query Language (JQL).Reference:JQL operators,Use advanced search with Jira Query Language (JQL)

asked 16/09/2024
Manish Chaudhary
40 questions

Question 45

Report Export Collapse

You want to report on your team's performance to the stakeholders. View one of the reports for your team:

Atlassian ACP-610 image Question 45 18247 09162024190126000000

Based only on the report shown, which statement about your teams performance is definitely true?

Become a Premium Member for full access
  Unlock Premium Member

Question 46

Report Export Collapse

You are responsible for three software products with individual release cycles.

Each product is managed in a different project.

Which report can provide an instant progress overview of all fix versions across all projects?

Become a Premium Member for full access
  Unlock Premium Member

Question 47

Report Export Collapse

Auditors group contains only two members; Adam and Eve.

You need to create a quick filter that shows overdue issues assigned to either of them

Which JQL query is always correct?

Become a Premium Member for full access
  Unlock Premium Member

Question 48

Report Export Collapse

All projects use only a single simplified workflow which has three statuses:

* Open

* In Progress

* Closed

Each status allows all statuses to transition to it

You need to identify oil issues that were in the Closed status at some point in their lifecycle.

Select the correct JQL query.

Become a Premium Member for full access
  Unlock Premium Member

Question 49

Report Export Collapse

Quang is a project administrator. He added several fields to his project screen. All team members have Edit Issues permission in this project. Which field can definitely be set all project team member-.'1

Become a Premium Member for full access
  Unlock Premium Member

Question 50

Report Export Collapse

You want to update a workflow that is not shared.

You are a project administrator and 'Extended project administration' is enabled.

Which two actions can you complete? (Choose two.)

Become a Premium Member for full access
  Unlock Premium Member
Total 75 questions
Go to page: of 8
Search

Related questions