What does ODI Stand for?

A.
Object Definition Instructions
A.
Object Definition Instructions
Answers
B.
Object Definition Instruments
B.
Object Definition Instruments
Answers
C.
Object Design Instruments
C.
Object Design Instruments
Answers
D.
Object Design Instruction
D.
Object Design Instruction
Answers
Suggested answer: D

Explanation:

Reference: http://blueprismforyou.blogspot.com/2018/03/bp-travel-create-quotes-solution-design.html

Which of the following statements describes the Object Design Instructions?

A.
Describes in detail the Blue Prism processes, components, business objects, work queues and credentials used to support the Blue Prism solution
A.
Describes in detail the Blue Prism processes, components, business objects, work queues and credentials used to support the Blue Prism solution
Answers
B.
Describes in detail a single Blue Prism Business Object, including all the actions in the object and all the inputs and outputs to those actions
B.
Describes in detail a single Blue Prism Business Object, including all the actions in the object and all the inputs and outputs to those actions
Answers
C.
Describes in detail the impact on the Operation from the delivery of the automated solution
C.
Describes in detail the impact on the Operation from the delivery of the automated solution
Answers
D.
Captures the flow of a business process to be developed within Blue Prism
D.
Captures the flow of a business process to be developed within Blue Prism
Answers
Suggested answer: B

What does OID Stand for?

A.
Operational Instructions Document
A.
Operational Instructions Document
Answers
B.
Object Impact Document
B.
Object Impact Document
Answers
C.
Operational Impact Document
C.
Operational Impact Document
Answers
D.
Object Instructions Document
D.
Object Instructions Document
Answers
Suggested answer: C

Explanation:

Reference: https://rpanerds.wordpress.com/2018/03/01/delivery-roadmap-or-life-cycle-of-blue-prism-process/

Which of the following best describes the support activity "Scheduling"?

A.
Operational (BAU) resources handling process scenarios out of scope
A.
Operational (BAU) resources handling process scenarios out of scope
Answers
B.
Developers handling unexpected scenarios where Blue Prism doesn't perform as designed
B.
Developers handling unexpected scenarios where Blue Prism doesn't perform as designed
Answers
C.
Blue Prism Controllers managing the workload and demand for the Digital Workforce
C.
Blue Prism Controllers managing the workload and demand for the Digital Workforce
Answers
D.
IT providing infrastructure failover and disaster recovery
D.
IT providing infrastructure failover and disaster recovery
Answers
Suggested answer: C

Which of the following should be covered with an RPA Service Model? (Choose three.)

A.
Exception case handling
A.
Exception case handling
Answers
B.
Technical support for application
B.
Technical support for application
Answers
C.
Product support from Blue Prism
C.
Product support from Blue Prism
Answers
D.
Hardware provisioning
D.
Hardware provisioning
Answers
Suggested answer: A, B, C

Explanation:

Reference: https://www.blueprism.com/robotic-operating-model

Which of the following best describes the support activity "Business Continuity"?

A.
Operational (BAU) resources handling process scenarios out of scope
A.
Operational (BAU) resources handling process scenarios out of scope
Answers
B.
Developers handling unexpected scenarios where Blue Prism doesn't perform as designed
B.
Developers handling unexpected scenarios where Blue Prism doesn't perform as designed
Answers
C.
Blue Prism Controllers managing the workload and demand for the Digital Workforce
C.
Blue Prism Controllers managing the workload and demand for the Digital Workforce
Answers
D.
IT providing infrastructure failover and disaster recovery
D.
IT providing infrastructure failover and disaster recovery
Answers
Suggested answer: D

Select the role that best matches the role objective? Objective: to manage the Certified Blue Prism Capability through delivery of new processes and support of existing processes.

A.
Program Manager
A.
Program Manager
Answers
B.
Automation Manager
B.
Automation Manager
Answers
C.
Delivery Lead
C.
Delivery Lead
Answers
D.
Process Analyst
D.
Process Analyst
Answers
Suggested answer: B

What objective does the Automation Manager have during the institutionalized phase?

A.
To manage the Certified Blue Prism Capability through delivery of new processes and support of existing processes
A.
To manage the Certified Blue Prism Capability through delivery of new processes and support of existing processes
Answers
B.
To manage the delivery of specific automated processes in line with the delivery management methodology
B.
To manage the delivery of specific automated processes in line with the delivery management methodology
Answers
C.
To lead Opportunity Assessments and create the Process Definitions
C.
To lead Opportunity Assessments and create the Process Definitions
Answers
Suggested answer: A

Which of the following best describes the role objective for a Process Analyst?

A.
To manage the implementation of a Certified Blue Prism Capability
A.
To manage the implementation of a Certified Blue Prism Capability
Answers
B.
To lead Opportunity Assessments, create the Process Definitions and support the testing as required
B.
To lead Opportunity Assessments, create the Process Definitions and support the testing as required
Answers
C.
To be the expert in all phases of Blue Prism solution development and associated methodology
C.
To be the expert in all phases of Blue Prism solution development and associated methodology
Answers
D.
To design, develop, test, run and support Blue Prism solutions
D.
To design, develop, test, run and support Blue Prism solutions
Answers
Suggested answer: B

Which of the following Blue Prism guides would a Process Analyst complete?

A.
Foundation Training
A.
Foundation Training
Answers
B.
Creating a Process Definition Document (PDD)
B.
Creating a Process Definition Document (PDD)
Answers
C.
Work Queues Guide
C.
Work Queues Guide
Answers
Suggested answer: B