Push is when work is:
B.
Delayed until later
C.
Given to people
D.
Expedited to meet a deadline
E.
Outsourced to a vendor
What is the primary risk addressed by the stakeholder vision milestone?
A.
That your architectural strategy is likely to work
B.
That your primary stakeholders agree to your strategy
C.
That the business case for the project is viable
D.
That a release plan for the project is realistic
Your team has written user stories to capture customer requirements, but they are concerned that the development team does not understand the overall business process. Which process goal is most likely to offer potential techniques to address this?
A.
Enterprise Architecture
B.
Ensure Production Readiness
C.
Explore Scope
D.
Improve Quality