Microsoft MB-335 Practice Test - Questions Answers, Page 15
List of questions
Question 141

A manufacturing company is implementing production in Dynamics 365 Supply Chain Management.
The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling in a graphical view.
You need to configure the system to meet the requirements.
Which three options should you configure? Each answer presents a partial solution.
NOTE: Each correct selection is worth one point.
Question 142

DRAG DROP
A manufacturer sends wiring harnesses to a vendor to be soldered to a connector. You create the subcontracting process in the bill of materials (BOM) and route to account for the items sent to the vendor.
You need to set up a new item model group for the service item.
Which three actions should you perform? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Question 143

HOTSPOT
A candy manufacturer uses Dynamics 365 Supply Chain Management.
A master planning run needs to prioritize the production jobs for fruit snacks by flavor and color every 16 days.
You need to configure the appropriate parameters in the coverage group.
What should you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
Question 144

A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management.
The company requires that employees register time against each machine on the shop floor.
You need to configure the system so that employees can register time.
Which two configurations must be set up? Each answer represents a partial solution
NOTE Each correct selection is worth one point.
Question 145

A company uses Dynamics 365 Supply Chain Management for Process manufacturing.
You are reviewing the planned production orders for the next two weeks. There are several production orders for the same product. One order is scheduled to run the week after another order.
You need to optimize the planned production orders.
What should you do?
Question 146

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen
A client subcontracts production work to a vendor for production operations.
You need to model subcontracting of route operations in production orders.
Solution: Ensure that the service product is stocked and is part of the Bill of Materials.
Does the solution meet the goal?
Question 147

A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.
Purchase orders for a raw material are created more frequently than needed. This results in missed discounts with the vendor who sells the raw material.
The raw material items have a 30-day lead time. The company is willing to delay sales and production order demand that may consume the raw material for up to 15 days to consolidate purchase orders.
You need to configure the setup to include lead time and consolidate purchase orders.
What should you configure?
Question 148

HOTSPOT
A company implements Dynamics 365 Supply Chain Management.
You run a master plan each week.
You need to resolve the issue in the scenario.
What should you do? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.
Question 149

HOTSPOT
A lean manufacturing company is implementing Dynamics 365 Supply Chain Management.
The manufacturer subcontracts a part of the production process.
Items must support the subcontracting process.
The subcontracted cost must be included in production
You need to configure the production process to meet the subcontracting requirements.
What should you do? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
Question 150

A customer produces light projection toys for holiday decorations throughout the year.
You are in the first month of a season. Production flows take one day to complete.
The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs.
You need to plan the jobs to be completed two weeks prior to the start of the next season.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
NOTE; Each correct selection is worth one point.
Question