ExamGecko
Home / Nutanix / NCS-Core / Practice Test 5
Ask Question

Nutanix NCS-Core Practice Test 5

00:00:00
Show Answer
Report Issue   Restart test

Question 1 / 40

While preparing for a new four-node cluster installation, the consultant has a Tech Review Call with the customer. The hardware is as follows:

* 4 nodes in 1 Block

* 8 x 10 GbE Ports

* 4 x 1 GbE IPMI Ports

* Adequate Ethernet ports are available

* Ethernet cables are correct and available

* Adequate rack space is available

Which remaining item must be confirmed as available onsite?

Crash Cart
Crash Cart
Fibre Channel switches
Fibre Channel switches
Redundant 208v power
Redundant 208v power
Redundant 110v power
Redundant 110v power
Comment (0)
Suggested answer: C
Explanation:

In the preparation for a new cluster installation, after ensuring that the basic physical requirements such as space, cabling, and hardware connectivity are met, it's crucial to confirm power requirements. For enterprise installations, particularly where high-powered equipment like a four-node cluster is involved, ensuring redundant power is critical. The question specifically mentions 'redundant' power, suggesting the need for a high-capacity solution typically found in 208v configurations in data centers, which provides more power efficiently and is standard for high-density computing hardware. Therefore, redundant 208v power should be confirmed as available onsite to support the new cluster's power needs effectively.

Reference: Nutanix Certified Services - Core (NCS-Core) training materials and installation best practices available through Nutanix University and the Nutanix Bible.

asked 23/09/2024
Marcel Janssen
40 questions