An ADM cycle can be used to establish an Architecture Capability within an organization. Which architecture produced in such a cycle would describe the architecture processes and organization structure?
Scenario:
Please read this scenario prior to answering the question
The ABC company specializes in the development of wind turbine blades for use in large-scale commercial wind energy production systems. The company has manufacturing facilities located in Palm Springs, California, Omaha, Nebraska, and Winnipeg, Manitoba. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturer's design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and greatly improved blade longevity. The company has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.
The company has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Review Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
The company has used T0GAF and its Architecture Development Method (ADM) to develop its automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies. They have adapted their Enterprise Architecture to closely follow the TOGAF 9 framework. All of the company's enterprise architects have been trained and certified on TOGAF 9. Recently, an architecture project was completed that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Manufacturing Architecture Board approved the plan for immediate implementation at each plant.
An Architecture Contract was developed that detailed the work needed to implement and deploy the new Automated Test System controller. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each site to ensure consistency.
Refer to the Scenario
You are the Lead Architect for this activity.
You have been asked to recommend the best approach to adopt to address the Chief Engineer's concern.
Based on TOGAF 9, which of the following is the best answer?
Scenario:
Please read this scenario prior to answering the question
The ABC company is an international agricultural company exporting bulbs, flowers and seeds worldwide. It is headquartered in Rotterdam in the Netherlands, and has sales and distribution centers in over 60 countries worldwide. Several of these centers include administrative, manufacturing, and research facilities.
To achieve full integration of their research capabilities with their development centers located in various climate zones, the company wants to develop strong self-directed teams in each location. It also wants to define new business models that are profitable while reducing their impact on the environment. The management is deeply committed to ensuring that the company is a world leader in socially responsible seed development with a business strategy that focuses on profitability through environmentally friendly operating processes.
The company international operations are subject to various legal and regulatory requirements. In areas such as genetically modified seeds, governmental controls are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was developing pest-resistant seeds.
The Governing Board is concerned, and as a result has approved the expenditure of resources to establish an Enterprise Architecture program. They have requested information about the status of projects that could impact regulatory compliance. They also want to enable the corporate legal staff and auditors to analyze proposed architectures to ensure that they are within the legal guidelines for a given location. In addition, the research organization should be able to see that the architecture is appropriate for its needs. TOGAF 9 has been mandated as the guiding framework for the development and evolution of the Enterprise
Architecture practice.
Refer to the Scenario
You have been appointed as the Lead Consultant.
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of all these parties. Based on
TOGAF 9, which of the following is the best answer?
Scenario:
Please read this scenario prior to answering the question
The ABC company is the prime contractor for the Telesto Unmanned Spacecraft program. Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. The company is moving aggressively to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.
To achieve this goal, the company needs to define Baseline and Target Architectures. These architectures must address key stakeholders' concerns such as:
Scenario:
Please read this scenario prior to answering the question
The ABC company is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of business.
The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture. The company has selected TOGAF 9 as the basis for its Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.
Refer to the Scenario
You are serving as the Chief Architect.
You have been asked to recommend the approach to take in the Preliminary Phase to ensure that the Corporate Board's concern is addressed. Based on
TOGAF 9, which of the following is the best answer?
Scenario:
Please read this scenario prior to answering the question
The ABC company started as an accounting and financial services company. It has expanded over the years and is now a leading North American IT and Business Services provider.
With numerous practice areas and a multitude of diverse engagements underway at any given time, overall engagement management has become challenging.
The company does not want to risk its outstanding reputation or its international certifications and CMM ratings. Senior partners must become team players, working to support the broader needs of the company and its shareholders.
The Enterprise Architecture team has been working to create the company's Enterprise Architecture framework to address these issues. The team has defined a preliminary framework and held workshops with key stakeholders to define a set of principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period.
An Architecture Review Board has been formed comprised of IT staff executives and executives from the major practice areas.
The Chief Executive Officer and Chief Information Officer have co-sponsored the creation of the Enterprise Architecture program. The Enterprise Architecture framework is based on TOGAF 9.
As the EA team prepare to formulate an Implementation plan, they have been asked by the CIO to assess the risks associated with the proposed architecture. He has received concerns from senior management that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.
Refer to the Scenario
You have been assigned to the role of Chief Enterprise Architect.
You have been asked to recommend an approach to satisfy the concerns raised. Based on TOGAF 9, which of the following is the best answer?
Scenario:
Please read this scenario prior to answering the question
The ABC company is a major supplier in the automotive industry, headquartered in Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.
The company is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The company Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9. At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their planning and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Scenario
You are serving as the Lead Enterprise Architect of the newly-formed Common ERP Deployment architecture project team.
As the Common ERP Deployment architecture project team assembles for its initial meeting, many of the participants have voiced concerns about the sweeping scope of the initiative. Others are confident that they know a solution that will work. During the meeting, a number of alternative recommendations for how to proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team evaluates different approaches to the problem and clarifies the requirements for the architecture. Based on TOGAF 9, which of the following is the best answer?
Scenario:
Please read this scenario prior to answering the Question.
The ABC Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache. This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets.
The Enterprise Architecture group at the company has been engaged in an architecture development project to create a secure networked collaboration system that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials. The Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years. The company Architecture Development Method is strictly based on TOGAF 9 with extensions required to support current good manufacturing practices and good laboratory practices in their target markets. The project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding Security Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. He has stated that the changes to the enterprise architecture for the new system will need to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The work will need to be done in stages and rolled out in geographical regions.
Refer to the Scenario
You are serving as the Lead Architect for the project team.
You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s). Based on TOGAF 9, which of the following is the best answer?
Scenario:
Please read this scenario prior to answering the Question.
The ABC company is a mobile telecommunications company formed through a series of mergers and acquisitions. They are yet to fully integrate the customer service systems for the most recent acquisitions, and as result, customer service has been a major concern for the Chief Technology Officer. Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer retention (Churn) rate have fallen below the industry average.
The Corporate Marketing group has published some new findings about customer satisfaction. The customers appear to be switching to AirLight, a competitor, because of superior customer service. The company actually has better coverage in nearly all markets than AirLight, and good roaming agreements that keep rates low for business travelers. But, customer satisfaction has remained low. The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to develop the enterprise-wide strategic plan.
They have developed a business scenario which contains a good conceptual model of what needs to be done, and also identifies the key requirements. This was used in preparing the proposal presented to the Executive Council and the Corporate Board. The planning for the program has been underway for several months. The company has selected TOGAF 9 as the basis for its Enterprise Architecture. The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged Customer Service System. It is anticipated that the overall program will take five years to complete, but there are some tactical projects that can commence immediately to address the situation.
The Executive Council has stated that the program should define specific initiatives to enable each regional business unit to create an implementation of the Customer Service System. The implementation must meet the needs of the business unit and still provide the information needed to enable major improvements to the customer.
Refer to the Scenario
You are serving as the Lead Architect for the Performance and Integrity project of the Customer Service System program.
The project has been chartered to address the architecture(s) required to support the Customer Service System from an infrastructure perspective. At the present time, the project team is conducting an architecture development project that is focused on the customer self-service capability, which was defined as part of the earlier strategic planning activities. This capability will enable customers to access their accounts, pay bills, request account reviews, and provision services from any web-enabled device.
The project team has gathered information about the self-service capability, developed a business scenario, and used the results to define an Architecture Vision for achieving the capability. You have been asked to recommend the course of action to complete the project. Based on TOGAF 9, which of the following is the best answer?
Scenario:
Please read this scenario prior to answering the question
Your role is consultant to the Lead Architect within a company that manufactures a variety of small electromechanical devices. As part of a corporate-wide Lean Manufacturing initiative, the company has defined a strategic architecture to improve its ability to meet consumer demand and improve its ability to manage its supply chain. The strategic architecture called for the consolidation of multiple Enterprise Resource Planning (ERP) applications that have been operating independently in several of the divisions' production facilities. The goal is to replace the functionality of the existing applications with a new ERP product running as a single instance in the company's primary data center.
The company has a mature enterprise architecture practice and uses TOGAF 9 for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.
Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness
Assessment started in Phase A. Based on all of these factors they have produced a risk assessment.
Because of the risks posed by the complexity of the current environment, it has been determined that a phased approach is needed to implement the target architectures. The overall implementation process is estimated to take several years.
Refer to the Scenario
The Implementation and Migration Plan v0.l, the draft Architecture Roadmap, and the Capability Assessment deliverables are now complete. You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.
Based on TOGAF 9, which of the following is the best answer?
Question