Scenario:

Please read this scenario prior to answering the Question

You are serving as the Lead Architect for the enterprise architecture team at the prime contractor for the Dreadnought Unmanned Aircraft System program.

Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. The decision has been made to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.

TOGAF 9 Is used for internal Enterprise Architecture activities, with an iterative approach for executing Architecture Development Method (ADM) projects.

At present, there are no particularly useful architectural assets related to this initiative, so all assets need to be acquired and customized or created from scratch.

The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving existing processes or systems.

The architect-re development project has put in place Its Architecture Capability for this project and has started a number of iteration cycles to develop the Architecture. Some tasks to address concerns related to the Business Architecture have been completed. The next immediate task is to address the Information

Systems Architectures. The Information Systems Architectures must address stakeholder concerns such as:

A.
Which procurement-related business processes are supported by zero, one, or many existing applications?
A.
Which procurement-related business processes are supported by zero, one, or many existing applications?
Answers
B.
What non-procurement applications will need to be integrated with any new procurement applications?
B.
What non-procurement applications will need to be integrated with any new procurement applications?
Answers
C.
What data will need to be shared?Refer to the Scenario [Note: You may need to refer to TOGAF 9 Chapter 35 in order to answer this question.]You have been asked to identify the most appropriate catalogs, matrices, and diagrams for this situation.Based on TOGAF 9, which of the following is the best answer?
C.
What data will need to be shared?Refer to the Scenario [Note: You may need to refer to TOGAF 9 Chapter 35 in order to answer this question.]You have been asked to identify the most appropriate catalogs, matrices, and diagrams for this situation.Based on TOGAF 9, which of the following is the best answer?
Answers
D.
in the early iterations of Architecture development, you would describe the Baseline Application Architecture with a System/Function matrix, and describe the Baseline Data Architecture using a Data Entity/Data Component catalog. In thelater Iterations of the Architecture Definition, you would describe the Target Application Architecture using Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with aSystem/Data matrix.
D.
in the early iterations of Architecture development, you would describe the Baseline Application Architecture with a System/Function matrix, and describe the Baseline Data Architecture using a Data Entity/Data Component catalog. In thelater Iterations of the Architecture Definition, you would describe the Target Application Architecture using Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with aSystem/Data matrix.
Answers
E.
In the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and anApplication Interaction matrix, and describe the Target Data Architecture with a System/Data matrix. In the later iterations of Architecture development, you would describe the Baseline Application Architecture with an Application and UserLocation diagram and a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.
E.
In the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and anApplication Interaction matrix, and describe the Target Data Architecture with a System/Data matrix. In the later iterations of Architecture development, you would describe the Baseline Application Architecture with an Application and UserLocation diagram and a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.
Answers
F.
In the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and anApplication Interaction matrix, and describe the Target Data Architecture with aData Entity/Business Function matrix and a System/Data matrix. In the later iterations of Architecture development, you would describe the BaselineApplication Architecture with a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.
F.
In the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and anApplication Interaction matrix, and describe the Target Data Architecture with aData Entity/Business Function matrix and a System/Data matrix. In the later iterations of Architecture development, you would describe the BaselineApplication Architecture with a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.
Answers
G.
In the early iterations of Architecture development, you would describe the Baseline Application Architecture with a Technology Portfolio catalog, and describe the Baseline Data Architecture with a Data diagram. In the later iterations ofArchitecture development, you would describe the Target Application Architecture with a System/Technology matrix, and describe the Target Data Architecture with a Data Dissemination diagram.
G.
In the early iterations of Architecture development, you would describe the Baseline Application Architecture with a Technology Portfolio catalog, and describe the Baseline Data Architecture with a Data diagram. In the later iterations ofArchitecture development, you would describe the Target Application Architecture with a System/Technology matrix, and describe the Target Data Architecture with a Data Dissemination diagram.
Answers
Suggested answer: C

Explanation:

In this the company prefers to implement commercial off the shelf package application with little customization and not concerned about preserving existing processes or systems.

Reference: 19.4 Approaches to Architecture Development.

Scenario:

Please read this scenario prior to answering the Question

You have been appointed as a consultant to the Lead Enterprise Architect of an international agricultural company that exports bulbs, flowers and seeds worldwide. The company has its headquarters in the Netherlands, and has sales and distribution centers in over 30 countries worldwide. Several of these centers include administrative, manufacturing, and research facilities.

To achieve full integration of their research capabilities with their development centers located in various climate zones, the company wants to develop strong self-directed teams in each location. It also wants to define new business models that are profitable while reducing their impact on the environment. The management team is deeply committed to ensuring that the company is a world leader in socially responsible seed development with a business strategy that focuses on profitability through environmentally friendly operating processes.

The international operations of the company are subject to legal and regulatory requirements for each country where they operate. The production of genetically modified seeds has governmental controls that are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was developing pest-resistant seeds.

The Governing Board is concerned about the risks posed in this complex global environment, and as a result has approved the expenditure of resources to establish an Enterprise Architecture program. They have requested to be informed about the status of projects that could impact regulatory compliance. They also want to enable the corporate legal staff and auditors to analyze proposed architectures to ensure that they are within the legal guidelines for a given location. In addition, the research organization should be able to see that the architecture is appropriate for its needs.

TOGAF 9 has been mandated as the framework for the development and evolution of the Enterprise Architecture practice. The Preliminary Phase has been completed to establish the enterprise architecture capability for this project.

Refer to the Scenario You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Governing Board, legal staff, auditors and the research organization. Based on TOGAF 9, which of the following is the best answer?

A.
You recommend that each project architecture activity is developed using a consistent modeling approach that is uniform across all architecture projects.Each architecture should be defined based on this fixed set of models so that allconcerned parties can examine the models to ensure that their issues and concerns have been addressed.
A.
You recommend that each project architecture activity is developed using a consistent modeling approach that is uniform across all architecture projects.Each architecture should be defined based on this fixed set of models so that allconcerned parties can examine the models to ensure that their issues and concerns have been addressed.
Answers
B.
You recommend that a special report be created for those groups that have sufficient power and level of interest. This report should summarize the key features of the architecture with respect to the particular location. Each of thesereports should reflect the stakeholders1 requirements.
B.
You recommend that a special report be created for those groups that have sufficient power and level of interest. This report should summarize the key features of the architecture with respect to the particular location. Each of thesereports should reflect the stakeholders1 requirements.
Answers
C.
You recommend that a set of models be created for each project architecture that can be used to ensure that the system will be compliant with the local regulations. Stakeholders should then view the models to verify that their concernshave been properly addressed.
C.
You recommend that a set of models be created for each project architecture that can be used to ensure that the system will be compliant with the local regulations. Stakeholders should then view the models to verify that their concernshave been properly addressed.
Answers
D.
You recommend that a stakeholder map be developed. This will allow the architects to define groups of stakeholders that share common concerns. A set of views should be defined to address the concerns for each group of stakeholders.Architecture models should then be created for each view to address the stakeholders' concerns.
D.
You recommend that a stakeholder map be developed. This will allow the architects to define groups of stakeholders that share common concerns. A set of views should be defined to address the concerns for each group of stakeholders.Architecture models should then be created for each view to address the stakeholders' concerns.
Answers
Suggested answer: A

Scenario:

Please read this scenario prior to answering the question

Your role is that of a consultant to the Lead Enterprise Architect in a company that develops wind turbines for use in wind farms. The company has three manufacturing facilities, one in North America, one in Asia, and one in Europe. Each of these facilities supplies the power industry in its region.

The company recognizes that the long-term technical potential of wind energy can address the current global dependency on carbon fuels. In order to do so this will require wind turbines to be installed over large areas of higher wind resources. In particular offshore wind farms can contribute substantially more energy than land stationed turbines.

The research arm of the company has pioneered the development of an offshore wind turbine design, with an improved turbine blade and power system, that will produce up to 20% more energy. This will allow the production of significantly more saleable energy. This new design is ready to go into production.

The company has a mature Enterprise Architecture practice supported by a cross-functional Architecture Board and uses the TOGAF standard. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.

As part of putting the new design into production, a pilot architecture project has defined an updated standard approach for controlling the automated test systems used to perform final quality assurance to perform final quality assurance. The Architecture Board approved the plan for immediate implementation at each plant.

Architecture Contracts have been developed that detail the work needed to implement and deploy the new Automated Test System controller for each location.

The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each location to ensure consistency.

Refer to the Scenario

You have been asked to recommend the best approach to address the Chief Engineer's concern.

Based on the TOGAF standard, Version 9.2, which of the following is the best answer?

A.
You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an externalparty, you ensure that it is a legally enforceable contract.You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
A.
You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an externalparty, you ensure that it is a legally enforceable contract.You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
Answers
B.
You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board andthe implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract.You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
B.
You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board andthe implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract.You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
Answers
C.
You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects,you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization.You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.
C.
You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects,you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization.You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.
Answers
D.
You use the Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of each completed turbine at each location and develop change requirements if necessary.You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local needs. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.
D.
You use the Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of each completed turbine at each location and develop change requirements if necessary.You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local needs. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.
Answers
Suggested answer: D

Scenario:

Please read this scenario prior to answering the Question

You are serving as the Chief Architect for a large, global commodities trading company which has been growing rapidly through a series of acquisitions.

Each business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.

As a result, the company has made the decision to introduce a single enterprise-wide application to consolidate information from several applications that exist across the lines of business. The application will be used by all business units and accessed by suppliers through well defined interfaces.

The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its trading partners.

The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.

TOGAF 9 has been selected for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.

Refer to the Scenario In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate Board. Based on TOGAF 9, which of the following is the best answer?

A.
You start by clarifying the intent that the Board has for raising these concerns. This enables you to understand the implications of the concern in terms of regulatory requirements and the potential impact on current business goals andobjectives. You propose that a security architect or security architecture team be allocated to develop a comprehensive security architecture and that this be considered an additional domain architecture.
A.
You start by clarifying the intent that the Board has for raising these concerns. This enables you to understand the implications of the concern in terms of regulatory requirements and the potential impact on current business goals andobjectives. You propose that a security architect or security architecture team be allocated to develop a comprehensive security architecture and that this be considered an additional domain architecture.
Answers
B.
You evaluate the implications of the Board's concerns by examining the security and regulatory impacts on business goals, business drivers and objectives.Based on your understanding, you then update the current security policy toinclude an emphasis on the concerns. You define architecture principles to form constraints on the architecture work to be undertaken in the project. You then allocate a security architect to ensure that security considerations are included in the architecture planning for all domains.
B.
You evaluate the implications of the Board's concerns by examining the security and regulatory impacts on business goals, business drivers and objectives.Based on your understanding, you then update the current security policy toinclude an emphasis on the concerns. You define architecture principles to form constraints on the architecture work to be undertaken in the project. You then allocate a security architect to ensure that security considerations are included in the architecture planning for all domains.
Answers
C.
You identify and document the security and regulatory requirements for the application and the data being collected. You ensure that written policies are put in place to address the requirements, and that they are communicated acrossthe organization, together with appropriate training for key employees. You identify constraints on the architecture and communicate those to the architecture team. You establish an agreement with the security architects defining their role within the ongoing architecture project.
C.
You identify and document the security and regulatory requirements for the application and the data being collected. You ensure that written policies are put in place to address the requirements, and that they are communicated acrossthe organization, together with appropriate training for key employees. You identify constraints on the architecture and communicate those to the architecture team. You establish an agreement with the security architects defining their role within the ongoing architecture project.
Answers
D.
You evaluate the implications of the concerns raised by the Corporate Board in terms of regulatory requirements and their impact on business goals and objectives. Based on this understanding, you then issue a Request for ArchitectureWork to commence an architecture development project to develop a solution that will address the concerns. You allocate a security architect to oversee the implementation of the new application that is being developed.
D.
You evaluate the implications of the concerns raised by the Corporate Board in terms of regulatory requirements and their impact on business goals and objectives. Based on this understanding, you then issue a Request for ArchitectureWork to commence an architecture development project to develop a solution that will address the concerns. You allocate a security architect to oversee the implementation of the new application that is being developed.
Answers
Suggested answer: B

Explanation:

Incorrect:

Not C: Implied that solution needs be developed to address the concern, instead of address the concern in the ERP solution itself.

Scenario:

Please read this scenario prior to answering the Question

You have been assigned the role of Chief Enterprise Architect within a leading North American information technology services company. The company has a number of service portfolios including infrastructure, applications, business process outsourcing, accounting, and financial services.

With numerous practice areas and a multitude of diverse engagements underway at any given time, overall engagement management within the company has become challenging. The company does not want to risk its outstanding reputation or its international certifications and CMM ratings.

The Chief Executive Officer and Chief Information Officer have co-sponsored the creation of an Enterprise Architecture prog-am based on TOGAF 9. An Architecture Board has been formed comprised of IT staff executives and executives from the major practice areas.

The Enterprise Architecture team has been working with the Strategic Planning team to create a strategic enterprise architecture to address these issues. The team has defined a framework and held workshops with key stakeholders to define a set of architecture principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period. This includes a solution architecture including three distinct transformations.

The CIO has made it clear that prior to the approval of the detailed Implementation and Migration plan, the EA team will need to assess the risks associated with the proposed architecture. He has received concerns from some of the senior partners that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.

Refer to the Scenario

You have been asked to recommend an approach to satisfy these concerns. Based on TOGAF 9, which of the following is the best answer?

A.
You recommend that before preparing the detailed Implementation and Migration plan, the EA team should review and consolidate the gap analysis results from Phases B to D to understand the transformations that are required toachieve the proposed Target Architecture. The EA team should assess the readiness of the organization to undergo change. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures.
A.
You recommend that before preparing the detailed Implementation and Migration plan, the EA team should review and consolidate the gap analysis results from Phases B to D to understand the transformations that are required toachieve the proposed Target Architecture. The EA team should assess the readiness of the organization to undergo change. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures.
Answers
B.
You recommend that the EA team apply an interoperability analysis to evaluate any potential issues across the Solution Architecture. This should include the development of a matrix showing the interoperability retirements. Once all ofthe concerns have been resolved, the EA team should finalize the Architecture Roadmap and the Implementation and Migration Plan.
B.
You recommend that the EA team apply an interoperability analysis to evaluate any potential issues across the Solution Architecture. This should include the development of a matrix showing the interoperability retirements. Once all ofthe concerns have been resolved, the EA team should finalize the Architecture Roadmap and the Implementation and Migration Plan.
Answers
C.
You recommend that the EA team apply the Business Transformation Readiness Assessment technique which will allow the risks associated with the transformations to be identified and mitigated for, it will also identify improvementactions to be worked into the Implementation and Migration Plan. A Business Value Assessment should be used to determine the business value and associated risks for the transformation.
C.
You recommend that the EA team apply the Business Transformation Readiness Assessment technique which will allow the risks associated with the transformations to be identified and mitigated for, it will also identify improvementactions to be worked into the Implementation and Migration Plan. A Business Value Assessment should be used to determine the business value and associated risks for the transformation.
Answers
D.
You recommend that the EA team should gather information about potential solutions from the appropriate sources. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine theTransition Architectures. A value realization process should then be established to ensure that the concerns raised are addressed.
D.
You recommend that the EA team should gather information about potential solutions from the appropriate sources. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine theTransition Architectures. A value realization process should then be established to ensure that the concerns raised are addressed.
Answers
Suggested answer: C

Scenario:

Please read this scenario prior to answering the question

You are serving as the Lead Enterprise Architect at a major supplier in the automotive industry. The company is headquartered in Cleveland, Ohio with manufacturing plants across the United States, Brazil, Germany, Japan and South Korea. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.

The company is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.

The Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.

At a recent meeting, the Architecture Board approved a Request for Architecture Work sponsored by the Chief Engineer of Global Manufacturing Operations.

The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.

The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of diving their planning and production scheduling from a remote centralized system. The Chief Engineer wants to know how these concerns can be addressed.

Refer to the Scenario

[Note: You should assume that the company has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.]

One of the earliest initiatives in the Enterprise Architecture program was the definition of a set of architecture principles. These now need to be updated to address the concerns raised.

You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution. Based on TOGAF 9, which of the following is the best answer?

A.
Common-use Applications, Control Technical Diversity, Ease of Use, Interoperability, Data is Shared, Data is Accessible, Data Security
A.
Common-use Applications, Control Technical Diversity, Ease of Use, Interoperability, Data is Shared, Data is Accessible, Data Security
Answers
B.
Business Continuity, Common-use Applications, Maximize Benefit to the Enterprise, Data is Shared, Data is Accessible, Data Security
B.
Business Continuity, Common-use Applications, Maximize Benefit to the Enterprise, Data is Shared, Data is Accessible, Data Security
Answers
C.
Technology Independence, Data Trustee, Information Management is Everybody's Business, IT Responsibility, Responsive Change Management
C.
Technology Independence, Data Trustee, Information Management is Everybody's Business, IT Responsibility, Responsive Change Management
Answers
D.
Service-orientation, Responsive Change Management, Business Continuity, Data is Accessible, Data Security
D.
Service-orientation, Responsive Change Management, Business Continuity, Data is Accessible, Data Security
Answers
Suggested answer: C

Scenario:

Please read this scenario prior to answering the Question

You have been assigned the role of Lead Enterprise Architect for a manufacturing firm that specializes in musical instruments. The firm has been established for over 100 years, operating in North America for most of that time. In the last ten years, the firm has expanded into European markets and will soon establish a market in Latin America. A future expansion into the Asia Pacific region is also planned.

The firm is organized into several business units that each focus on manufacturing particular families of instruments such as brass, woodwind, and percussion.

Each business unit has acquired other producers to expand its manufacturing capacity. This has resulted in a complex environment with a high diversity of business and manufacturing systems.

The Enterprise Architecture (EA) program within the firm has been functioning for several years. It has made significant progress in consolidating the technology portfolio and establishing key standards. The CIO and the COO are pint sponsors of the EA program. The EA program is mature, with an active Architecture Board and a well-defined architecture process and standard content templates based on the TOGAF 9 Architecture Content Framework. The EA process framework is well coordinated with the PMO, Systems Development, and Operations functions.

The firm has completed a strategic plan to reorganize its Sales & Marketing organization according to the four target geographic markets. One of the goals of this reorganization is to improve the ability of Marketing to collect more meaningful market analytics that will enable each sector to better address market needs with effective marketing campaigns and global product presence.

A Request for Architecture Work to address the goals of the reorganization has been approved. As the architecture team commences its work, the CIO has expressed concerns about whether the firm will be able to adapt to the proposed architecture and how to manage the associated risks.

Refer to the Scenario

You have been asked how to address the concerns of the CIO. Based on TOGAF 9, which of the following is the best answer?

A.
In Phase B, the team should create a set of views that will enable them to identify the factors that will influence the successful introduction of the architecture into the organization. There should then be an assessment of each factor on amaturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then be used to assess the initial risks associated with the proposed architecture.
A.
In Phase B, the team should create a set of views that will enable them to identify the factors that will influence the successful introduction of the architecture into the organization. There should then be an assessment of each factor on amaturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then be used to assess the initial risks associated with the proposed architecture.
Answers
B.
In Phase A the team should analyze their risk by completing an Implementation Factor Assessment and Deduction Matrix to identify the particular risks associated with the implementation and deployment. The matrix should include a listof factors to be considered, their descriptions, and constraints that should be taken into account. These factors can then used to assess the initial risks associated with the proposed architecture.
B.
In Phase A the team should analyze their risk by completing an Implementation Factor Assessment and Deduction Matrix to identify the particular risks associated with the implementation and deployment. The matrix should include a listof factors to be considered, their descriptions, and constraints that should be taken into account. These factors can then used to assess the initial risks associated with the proposed architecture.
Answers
C.
In Phase A, the team should use the Business Transformation Readiness Assessment technique to identify the factors that will influence the successful introduction of the architecture into the organization. The assessment should includedetermining the readiness rating for each factor based on a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then used to assess the initial risks associated with the proposed architecture.
C.
In Phase A, the team should use the Business Transformation Readiness Assessment technique to identify the factors that will influence the successful introduction of the architecture into the organization. The assessment should includedetermining the readiness rating for each factor based on a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then used to assess the initial risks associated with the proposed architecture.
Answers
D.
In Phase A, the team should conduct a Business Scenario to identify the stakeholders' concerns and the resulting retirements. Once the retirements have been identified, they can be assessed in terms of their risks. The risks should beevaluated in terms of how they could be avoided, transferred, or mitigated. Any risks that cannot be resolved should be identified as residual risks and their disposition should be decided by the Architecture Board.
D.
In Phase A, the team should conduct a Business Scenario to identify the stakeholders' concerns and the resulting retirements. Once the retirements have been identified, they can be assessed in terms of their risks. The risks should beevaluated in terms of how they could be avoided, transferred, or mitigated. Any risks that cannot be resolved should be identified as residual risks and their disposition should be decided by the Architecture Board.
Answers
Suggested answer: C

Explanation:

This scenario is upon Request for Architecture Work, which kicks off the Phase A, the Architecture Vision. In this phase, risk should be considered, which is also the CIO's concern in this scenario. One of the approaches in TOGAF is the Business Transformation Readiness Assessment.

Incorrect:

Not B: Implementation Factor Assessment and Deduction Matrix is used for implementation & migration planning (not B).

Scenario

Please read this scenario prior to answering the Question

You are serving as the Lead Architect for an insurance company, which has been formed through the merger of three previously independent companies. The company now consists of three divisions with the same names and division headquarters as their predecessors.

The lack of integration between the three divisions has increasingly caused problems in the handling of customer and financial information. The inability to share information has resulted in lost opportunities to leverage the synergies that should have been possible as a result of the merger. At present, each division maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, and claims information, each division has different ways of defining these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.

As a result, the company has made the decision to introduce a common web portal, contact center software suite, and document management system. Also the company has selected a single enterprise-wide customer relationship management (CRM) application to consolidate information from several applications that exist across the divisions. The application will be used by each of the divisions and accessed by third party partners through well defined interfaces.

The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its partners.

The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the migration teams in each division. The CIO has also formed a crossfunctional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.

TOGAF 9 has been selected as the core framework for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.

Refer to the Scenario

As part of the process for establishing the Enterprise Architecture department, you are developing a set of architecture principles to guide the activities.

You need to recommend the best approach for this work.

Based on TOGAF, which of the following is the best answer?

A.
You would review the mission statements for the company and its divisions, together with the corporate business goals and business drivers. Based on that review, you would work closely with the key stakeholders and the ArchitectureBoard to define the architecture principles. You would ensure that they actively promote the alignment of IT with the corporate business strategies. You would then hold review meetings with the relevant stakeholders, including senior management, ensuring their support.
A.
You would review the mission statements for the company and its divisions, together with the corporate business goals and business drivers. Based on that review, you would work closely with the key stakeholders and the ArchitectureBoard to define the architecture principles. You would ensure that they actively promote the alignment of IT with the corporate business strategies. You would then hold review meetings with the relevant stakeholders, including senior management, ensuring their support.
Answers
B.
You would gather information from credible industry sources in the insurance business. Based on that information, you would assess current trends and apply them to defining a set of principles that embody best practices. You wouldselect architecture principles that do not conflict with each other and that should be stable. You would ensure that all the principles are realistic and avoid including principles that are too obvious.
B.
You would gather information from credible industry sources in the insurance business. Based on that information, you would assess current trends and apply them to defining a set of principles that embody best practices. You wouldselect architecture principles that do not conflict with each other and that should be stable. You would ensure that all the principles are realistic and avoid including principles that are too obvious.
Answers
C.
You would analyze the mission statements for the company and each of its divisions, together with the corporate business goals. Based on that analysis, you would define a set of architecture principles and review them with the CIO.When developing the principles, you would ensure that they actively promote the alignment of IT with the business strategies and initiatives of the company.You would then seek the endorsement of the CIO and senior management.
C.
You would analyze the mission statements for the company and each of its divisions, together with the corporate business goals. Based on that analysis, you would define a set of architecture principles and review them with the CIO.When developing the principles, you would ensure that they actively promote the alignment of IT with the business strategies and initiatives of the company.You would then seek the endorsement of the CIO and senior management.
Answers
D.
You would define a set of principles that support the preferred best practices embodied in the Enterprise Architecture department charter. You would publish the principles on the corporate intranet to ensure widespread acceptance andcompliance. You would then schedule regular periodic Compliance Assessments with each of the divisions to check that they have made satisfactory progress toward meeting the objectives and conditions embodied in the principles.
D.
You would define a set of principles that support the preferred best practices embodied in the Enterprise Architecture department charter. You would publish the principles on the corporate intranet to ensure widespread acceptance andcompliance. You would then schedule regular periodic Compliance Assessments with each of the divisions to check that they have made satisfactory progress toward meeting the objectives and conditions embodied in the principles.
Answers
Suggested answer: A

Scenario:

Please read this scenario prior to answering the Question

You are the Lead Architect for a firm that manufactures ball bearings used in industrial equipment applications. They have manufacturing operations in several cities in the United States, Germany, and the United Kingdom.

The firm has traditionally allowed each manufacturing plant to drive its own production planning systems. Each plant has its own custom Materials Requirements

Planning, Master Production Scheduling, Bill of Materials, and Shop Floor Control systems.

"Just In Time" manufacturing techniques are used to minimize wastes caused by excessive inventory and work in process. The increasingly competitive business environment has compelled the firm to improve its business capability to be more responsive to the needs of industrial customers. To support this capability, the firm has decided to implement an Enterprise Resource Planning (ERP) solution that will enable it to better coordinate its manufacturing capacity to match the demands for its products across all plants. In addition, there are also new European regulations coming into force to which their manufacturing processes must conform in the next six months.

As part of the implementation process, the Enterprise Architecture (EA) department has begun to implement an architecture process based on TOGAF 9. The CIO is the sponsor of the activity. The Chief Architect has directed that the program should include formal modeling using the Architecture Content Framework and the TOGAF Content Metamodel. This will enable support for the architecture tooling that the firm uses for its EA program.

The Chief Architect has stated that in order to model the complex manufacturing process it will be necessary to model processes that are event-driven. Also, in order to consolidate applications across several data centers it will be necessary to model the location of IT assets. In particular, the end goal is to have the single ERP application running in a single data center.

Currently the project is in the Preliminary Phase, and the architects are tailoring the Architecture Development Method (ADM) and Architecture Content Framework to fit into the corporate environment.

Refer to the Scenario

You have been asked to recommend a response to the Chief Architect's request to tailor the TOGAF Content Metamodel. Based on TOGAF 9, which of the following is the best answer?

A.
You recommend that the architecture team incorporate the Process Modeling and Infrastructure Consolidation extensions into their tailored ContentMetamodel. As the environment is process-centric this will enable them to model themanufacturing processes and store information to support regulatory compliance. It also includes views useful for managing the consolidation of applications into a single data center.
A.
You recommend that the architecture team incorporate the Process Modeling and Infrastructure Consolidation extensions into their tailored ContentMetamodel. As the environment is process-centric this will enable them to model themanufacturing processes and store information to support regulatory compliance. It also includes views useful for managing the consolidation of applications into a single data center.
Answers
B.
You recommend that the architecture team incorporate the Process Modeling and Governance extensions into their tailored Content Metamodel. This is suitable as this is a significant IT change that will impact its operational models. Thiswill ensure that they include specific entities and attributes that will allow them to model the event-driven nature of the manufacturing processes more precisely.
B.
You recommend that the architecture team incorporate the Process Modeling and Governance extensions into their tailored Content Metamodel. This is suitable as this is a significant IT change that will impact its operational models. Thiswill ensure that they include specific entities and attributes that will allow them to model the event-driven nature of the manufacturing processes more precisely.
Answers
C.
You recommend that the architecture team incorporates the Governance and Motivation Extensions into their tailored Content Metamodel. This would allow modeling of the target milestones they want to achieve with this consolidation ofapplication to a single data center. These extensions will also enable demonstration of regulatory compliance for the manufacturing process.
C.
You recommend that the architecture team incorporates the Governance and Motivation Extensions into their tailored Content Metamodel. This would allow modeling of the target milestones they want to achieve with this consolidation ofapplication to a single data center. These extensions will also enable demonstration of regulatory compliance for the manufacturing process.
Answers
D.
You recommend that the architecture team incorporates the Data and Services Extensions into their tailored Content Metamodel. This would allow modeling of the location of IT assets and ensure regulatory compliance for themanufacturing process. It will also allow for identification of redundant duplication of capability which will be needed for a successful consolidation to a single data center.
D.
You recommend that the architecture team incorporates the Data and Services Extensions into their tailored Content Metamodel. This would allow modeling of the location of IT assets and ensure regulatory compliance for themanufacturing process. It will also allow for identification of redundant duplication of capability which will be needed for a successful consolidation to a single data center.
Answers
Suggested answer: B

Scenario:

Please read this scenario prior to answering the Question

You are serving as the Chief Architect for a large, global commodities trading company which has been growing rapidly through a series of acquisitions.

Each business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.

As a result, the company has made the decision to introduce a single enterprise-wide application to consolidate information from several applications that exist across the lines of business. The application will be used by all business units and accessed by suppliers through well defined interfaces.

Refer to the Scenario

As part of the process for establishing the Enterprise Architecture department, you are developing a set of architecture principles to guide the activities. You need to specify the best approach for this work.

Based on TOGAF 9, which of the following is the best answer?

A.
You gather information from credible industry sources in the commodities business. Based on that, you assess current trends and apply that to defining a set of principles that embody best practices. You select architecture principles thatdo not conflict with each other and that should be stable. You ensure that all the principles are realistic and avoid including principles that are obvious.
A.
You gather information from credible industry sources in the commodities business. Based on that, you assess current trends and apply that to defining a set of principles that embody best practices. You select architecture principles thatdo not conflict with each other and that should be stable. You ensure that all the principles are realistic and avoid including principles that are obvious.
Answers
B.
You examine the mission statements for the company and each of its businesses, together with the corporate value statements. Based on that, you define a set of principles and review with the CIO. When developing the principles, youensure that they actively promote the alignment of IT with the business strategies and initiatives of the company. You then seek the endorsement of the CIO and senior management.
B.
You examine the mission statements for the company and each of its businesses, together with the corporate value statements. Based on that, you define a set of principles and review with the CIO. When developing the principles, youensure that they actively promote the alignment of IT with the business strategies and initiatives of the company. You then seek the endorsement of the CIO and senior management.
Answers
C.
You define a set of principles that support the preferred best practices embodied in the Enterprise Architecture department charter. You publish the principles on the corporate intranet to ensure widespread acceptance and compliance.You then schedule regular periodic Compliance Assessments with individual business units to check that they have made satisfactory progress toward meeting the objectives and conditions embodied in the principles.
C.
You define a set of principles that support the preferred best practices embodied in the Enterprise Architecture department charter. You publish the principles on the corporate intranet to ensure widespread acceptance and compliance.You then schedule regular periodic Compliance Assessments with individual business units to check that they have made satisfactory progress toward meeting the objectives and conditions embodied in the principles.
Answers
D.
You examine the mission statements for the company and each of its businesses, together with the corporate value statements. Based on that, you work with the Architecture Board to define the principles. When developing the principlesyou ensure that they actively promote the alignment of IT with the corporate business strategies. You then hold a series of review meetings with all the relevant stakeholders, including senior management, ensuring their support.
D.
You examine the mission statements for the company and each of its businesses, together with the corporate value statements. Based on that, you work with the Architecture Board to define the principles. When developing the principlesyou ensure that they actively promote the alignment of IT with the corporate business strategies. You then hold a series of review meetings with all the relevant stakeholders, including senior management, ensuring their support.
Answers
Suggested answer: D
Total 411 questions