Scrum PSM II Practice Test - Questions Answers
List of questions
Related questions
The relationship between the Product Owner and the Developers has degraded over time.
The Developers are growing increasingly angry with the Product Owner for changing the requirements all the time and not being available enough. The Product Owner is angry with the Developers for changing requirements during implementation. What guidance should the Scrum Master offer?
(choose the best answer)
In an environment where user acceptance testing is required before the Increment can be put into production, a development manager proposes to have user acceptance testing done every third Sprint, because the feedback from the user acceptance tests are disrupting work in Sprints. Is this a good idea?
(choose the best answer)
Which statement about the Sprint Goal is incorrect?
(choose the best answer)
Which two of these situations best demonstrate that a Scrum Team is self-managing?
(choose the best two answers)
Scrum requires a Definition of Done. Which phrases describe the purpose of the Definition of Done?
(choose the best three answers)
A Scrum Team consists of Developers working from globally distributed locations. Organizing the Scrum events requires conferencing tools that are not easily available within the organization. The Developers propose doing a Daily Scrum only on Tuesdays. Which are the most appropriate responses for their Scrum Master?
(choose the best two answers)
Marian is a product Owner working on a Scrum Team on a new release for her product. Based on the average velocity of the previous release Marian estimated the project to take seven Sprints. Average velocity In the previous release was thirteen completed units of work per Sprint Development is three Sprints underway, with tour more Sprints to go until the release.
Product Backlog has been stable.
Over the first three Sprints, the Developers report their average velocity is nine, while not having fully tested all the delivered functionality. The Developers estimate that the unfinished testing would have required of a Sprints time. The Developers believe that the required velocity of thirteen is within their reach. What is the most effective way to recover?
(choose the best answer)
During Sprint Planning, Developers work with the Product Owner to create a forecast for the Sprint. A forecast is a selection of Product Backlog items that the Developers believe are possible to get done by the end of the Sprint. Select two things that explain what done means.
(choose the best two answers)
How should requirements be distributed when multiple Scrum Teams work on the same product?
(choose the best answer)
Your organization always stresses the importance of on-time delivery and reliability. A manager has detected that your team's progress is too slow. They feel that your team's velocity needs to be 10% higher.
The organization expects you, as the Scrum Master, to make it happen. How do you respond?
(choose the best two answers)
Question