ExamGecko
Home Home / Scrum / PSM II

Scrum PSM II Practice Test - Questions Answers, Page 8

Question list
Search
Search

Related questions











What is one way to determine if the Product Owner is interacting with the Developers enough throughout a Sprint?

(choose the best answer)

A.
The Developers should determine the percentage of time the Product Owner is required to be present and monitor whether the Product Owner's average presence is around this figure.
A.
The Developers should determine the percentage of time the Product Owner is required to be present and monitor whether the Product Owner's average presence is around this figure.
Answers
B.
Check the Daily Scrum reports to see whether the Product Owner was present at the majority of the Daily Scrum meetings.
B.
Check the Daily Scrum reports to see whether the Product Owner was present at the majority of the Daily Scrum meetings.
Answers
C.
Observe whether the Developers need to ask the Product Owner questions at times other than during the Daily Scrum.
C.
Observe whether the Developers need to ask the Product Owner questions at times other than during the Daily Scrum.
Answers
D.
Product Owners and Developers are satisfied with the increment.
D.
Product Owners and Developers are satisfied with the increment.
Answers
Suggested answer: D

Explanation:

The best way to determine if the Product Owner is interacting with the Developers enough throughout a Sprint is to observe whether both parties are satisfied with the Increment.The Increment is a concrete stepping stone toward the Product Goal1.It must be usable and meet the Definition of Done1.The Product Owner is accountable for maximizing the value of the product resulting from the work of the Developers1.The Developers are accountable for creating a valuable, useful, and potentially releasable Increment every Sprint1. Therefore, if both the Product Owner and the Developers are happy with the quality and value of the Increment, it means that they have communicated and collaborated effectively throughout the Sprint.

Some reasons why the other options are not correct are:

A: The Developers should determine the percentage of time the Product Owner is required to be present and monitor whether the Product Owner's average presence is around this figure. This option is not correct because it implies that there is a fixed or optimal amount of time that the Product Owner should spend with the Developers, which may not be true. The Product Owner's interaction with the Developers may vary depending on the context, complexity, and uncertainty of the product and the Sprint.The Scrum Guide does not prescribe any specific time or frequency for the Product Owner's involvement with the Developers1.The Product Owner should be available to provide guidance and feedback to the Developers as needed, but not interfere with their self-organization and autonomy1.

B: Check the Daily Scrum reports to see whether the Product Owner was present at the majority of the Daily Scrum meetings. This option is not correct because it assumes that the Daily Scrum is a meeting where the Product Owner should be present, which is not true.The Daily Scrum is an event for and by the Developers12, not for reporting or accountability to anyone else.The Product Owner may attend as an observer or a collaborator, but only if invited by the Developers12. The presence or absence of the Product Owner at the Daily Scrum does not indicate how much they interact with the Developers throughout the Sprint.

C: Observe whether the Developers need to ask the Product Owner questions at times other than during the Daily Scrum. This option is not correct because it implies that asking questions is a sign of insufficient interaction, which may not be true. Asking questions is a natural and healthy part of communication and collaboration between the Product Owner and the Developers. It shows that they are engaged, curious, and willing to learn from each other. It also helps them to clarify requirements, expectations, and feedback, and to resolve any ambiguities or conflicts. Asking questions does not necessarily mean that there is a lack of interaction, but rather that there is a need for more information or clarification.

What is an Increment? | Scrum.org

What Is a Daily Standup? | A Guide to Running Effective Standup Meetings | Atlassian

Which two options describe how project budgeting and financial forecasting work in Scrum?

(choose the best two answers)

A.
Scrum does not align with traditional accounting practices. The financial department needs to be given a fixed cost per Sprint per team.
A.
Scrum does not align with traditional accounting practices. The financial department needs to be given a fixed cost per Sprint per team.
Answers
B.
Several Sprints may be funded as a single release, with the result of each Sprint being releasable product
B.
Several Sprints may be funded as a single release, with the result of each Sprint being releasable product
Answers
C.
The only funding is for the run cost (time and materials) of the Scrum Teams, so no budgeting process is needed_
C.
The only funding is for the run cost (time and materials) of the Scrum Teams, so no budgeting process is needed_
Answers
D.
It is ideally revisited as frequently as each Sprint to ensure value is being delivered for the investment spent.
D.
It is ideally revisited as frequently as each Sprint to ensure value is being delivered for the investment spent.
Answers
Suggested answer: B, D

Explanation:

Short Scrum is a framework for delivering value to customers and stakeholders in an iterative and incremental way. Scrum does not prescribe how project budgeting and financial forecasting should be performed, but it does provide some principles and practices that can help with this process.

One of these principles is that each Sprint should produce a potentially releasable product Increment that delivers value and meets the Definition of Done. This means that several Sprints may be funded as a single release, with the result of each Sprint being releasable product12. This allows the Product Owner to decide when to release the product based on the feedback from the customers and stakeholders, and the market conditions.

Another principle is that Scrum promotes transparency, inspection, and adaptation. This means that the budgeting and forecasting process should be revisited as frequently as each Sprint to ensure value is being delivered for the investment spent13. This allows the Scrum Team to inspect the outcomes of the delivered Sprint Increments, compare them with the expected benefits and costs, and adapt the product backlog and the release plan accordingly.

Scrum does not align with traditional accounting practices that require fixed scope, cost, and time. However, this does not mean that Scrum Teams do not need a budgeting process or that they only need to cover the run cost (time and materials) of the Scrum Teams. Scrum Teams still need to estimate the size and value of the product backlog items, forecast the delivery date and cost of the product or release, and track the actual spending and revenue of the product or release43. The difference is that these estimates and forecasts are based on empirical data from previous Sprints, rather than on upfront assumptions or guesses. They are also subject to change as new information emerges or new requirements arise.

Scrum Guide 2020, section ''The Sprint'', ''The Increment'', ''Empiricism''.

Tips for Effective Agile Budgeting and Forecasting | Toptal, section ''Establish Context and Set Expectations'', ''Budget for Value''.

Project forecasts and budgets | Microsoft Learn, section ''Project forecasting''.

Planning and Budgeting in Scrum Projects - PMHut, section ''Budgeting in Scrum Projects''.

What action should a Scrum Master take if the Development Team has decided that Retrospectives are no longer necessary?

A.
Start facilitating more productive and useful Retrospectives.
A.
Start facilitating more productive and useful Retrospectives.
Answers
B.
Suggest reducing the frequency of the Retrospectives.
B.
Suggest reducing the frequency of the Retrospectives.
Answers
C.
Extend the Sprint time-box in order to fit the Retrospectives.
C.
Extend the Sprint time-box in order to fit the Retrospectives.
Answers
D.
Comply with the team's decision.
D.
Comply with the team's decision.
Answers
Suggested answer: A

What does the Scrum Team commit to each Sprint?

(choose the best three answers)

A.
Getting all the forecast work in the Sprint Plan done
A.
Getting all the forecast work in the Sprint Plan done
Answers
B.
Increasing velocity
B.
Increasing velocity
Answers
C.
Working towards the Sprint Goal.
C.
Working towards the Sprint Goal.
Answers
D.
Seeking stakeholder feedback.
D.
Seeking stakeholder feedback.
Answers
E.
Having the Product Owner available to the Developers on a daily basis
E.
Having the Product Owner available to the Developers on a daily basis
Answers
F.
Upholding transparency
F.
Upholding transparency
Answers
Suggested answer: C, D, F

Explanation:

According to the Scrum Guide 2020, the Scrum Team commits to achieving the Sprint Goal and creating a valuable product Increment every Sprint1.The Sprint Goal is a short statement that provides direction and focus for the Scrum Team throughout the Sprint2.The product Increment is a concrete and usable outcome that meets the Definition of Done and adds value to the product3. Therefore, the Scrum Team commits to:

Working towards the Sprint Goal.This means that the Scrum Team collaborates and coordinates their work to deliver a product Increment that satisfies the Sprint Goal.The Sprint Goal is chosen by the Scrum Team during Sprint Planning, based on the Product Backlog items that they forecast to complete in the Sprint2.The Sprint Goal provides coherence and alignment for the Scrum Team, and helps them cope with complexity and uncertainty4.

Seeking stakeholder feedback.This means that the Scrum Team engages with the stakeholders and customers who have an interest or influence on the product. The Scrum Team seeks their feedback to inspect and adapt the product Increment and the Product Backlog, and to validate their assumptions and hypotheses. The Sprint Review is an event where the Scrum Team and the stakeholders collaborate on what was done in the Sprint and what to do next.

Upholding transparency.This means that the Scrum Team makes all aspects of their work visible to those who are responsible for the outcome. Transparency enables inspection and adaptation, which are essential for empiricism. The Scrum Team upholds transparency by using the Scrum artifacts (Product Backlog, Sprint Backlog, and Increment) as sources of information and progress, and by having frequent and honest communication among themselves and with the stakeholders.

The other options are not correct because:

Getting all the forecast work in the Sprint Plan done.This option is incorrect because it implies that the Scrum Team is committed to a fixed scope of work, rather than a flexible goal. The Scrum Guide 2020 states that ''the Developers do not commit to completing all of the work planned during a Sprint Planning'' but rather ''they plan their work as they perform it throughout the Sprint''. The Scrum Team can modify their Sprint Backlog during the Sprint as needed, as long as they do not endanger the Sprint Goal.

Increasing velocity.This option is incorrect because it implies that the Scrum Team is committed to a metric that is not part of the Scrum framework. Velocity is a measure of how much work a team can deliver in a given time period, usually based on story points or hours. However, velocity is not a reliable indicator of value or quality, and it can vary depending on many factors, such as team size, complexity, dependencies, etc. The Scrum Guide 2020 does not mention velocity as a commitment or an artifact of the Scrum Team.

Having the Product Owner available to the Developers on a daily basis.This option is incorrect because it implies that the Product Owner is not part of the Scrum Team, but rather an external stakeholder. The Scrum Guide 2020 states that ''the Product Owner is one person who is a member of the Scrum Team'' and ''is accountable for maximizing value resulting from work of Developers''. The Product Owner collaborates closely with the Developers throughout the Sprint, not only by being available, but also by providing vision, guidance, feedback, and clarification.

Which statements are true about the Sprint Goal?

(choose the best two answers)

A.
Sprint Goals often change during the Sprint as new insights emerge during the work.
A.
Sprint Goals often change during the Sprint as new insights emerge during the work.
Answers
B.
During Sprint Planning, the Scrum Team crafts a Sprint Goal based on an objective that the Product Owner would like to achieve that Sprint.
B.
During Sprint Planning, the Scrum Team crafts a Sprint Goal based on an objective that the Product Owner would like to achieve that Sprint.
Answers
C.
Sprint Goals give Developers flexibility and creativity on how to implement functionality during the Sprint
C.
Sprint Goals give Developers flexibility and creativity on how to implement functionality during the Sprint
Answers
D.
The use of Sprint Goals is optional in the Scrum Framework
D.
The use of Sprint Goals is optional in the Scrum Framework
Answers
Suggested answer: B, C

Explanation:

According to the Scrum Guide 2020, the Sprint Goal is a short statement that provides direction and focus for the Scrum Team throughout the Sprint1.The Sprint Goal is chosen by the Scrum Team during Sprint Planning, based on the Product Backlog items that they forecast to complete in the Sprint1.The Sprint Goal also gives Developers flexibility and creativity on how to implement functionality during the Sprint, as long as they do not endanger the Sprint Goal1. Therefore, the statements that are true about the Sprint Goal are:

During Sprint Planning, the Scrum Team crafts a Sprint Goal based on an objective that the Product Owner would like to achieve that Sprint.This statement is true because it reflects the purpose and process of creating a Sprint Goal.The Product Owner proposes an objective for the Sprint, based on the current state of the product and the stakeholders' needs2.The Developers then select the Product Backlog items that support that objective, and craft a Sprint Goal that expresses what value they will deliver in the Sprint2.

Sprint Goals give Developers flexibility and creativity on how to implement functionality during the Sprint.This statement is true because it reflects the benefit and outcome of having a Sprint Goal.The Sprint Goal is not a fixed scope of work, but a flexible goal that guides the Developers' decisions and actions3.The Developers can modify their Sprint Backlog during the Sprint as needed, as long as they do not endanger the Sprint Goal1.The Sprint Goal also encourages the Developers to work together rather than on separate initiatives3.

The other statements are not true because:

Sprint Goals often change during the Sprint as new insights emerge during the work.This statement is false because it contradicts the Scrum framework, which defines the Sprint Goal as a commitment by the Developers that does not change during a Sprint1.The Sprint Goal provides coherence and alignment for the Scrum Team, and helps them cope with complexity and uncertainty3. Changing the Sprint Goal during a Sprint would undermine its value and impact, and create confusion and waste.

The use of Sprint Goals is optional in the Scrum Framework.This statement is false because it contradicts the Scrum framework, which defines the Sprint Goal as a mandatory element of each Sprint1.The Scrum Guide 2020 states that ''the entire Scrum Team is accountable for creating a valuable, useful Increment every Sprint'' and ''the Developers commit to achieving the Sprint Goal''1. Without a Sprint Goal, there would be no clear direction or focus for the Scrum Team, and no way to measure their progress or success.

Creating a forecast for a Sprint tends to run more smoothly when the Product Backlog items that are discussed are well understood and actionable. Which approach would you recommend to ensure well understood and actionable Product Backlog items at Sprint Planning?

(choose the best answer)

A.
The Developers use some time in each Sprint to analyze, estimate and design high- ordered Product Backlog items.
A.
The Developers use some time in each Sprint to analyze, estimate and design high- ordered Product Backlog items.
Answers
B.
The Product Owner works with the stakeholders to prepare Product Backlog items outside of the Sprint so the Developers will not be disrupted.
B.
The Product Owner works with the stakeholders to prepare Product Backlog items outside of the Sprint so the Developers will not be disrupted.
Answers
C.
A separate Scrum Team of business analysts and testers analyze high-ordered requirements one Sprint ahead of development.
C.
A separate Scrum Team of business analysts and testers analyze high-ordered requirements one Sprint ahead of development.
Answers
D.
The analysts on the Scrum Team document high-ordered Product Backlog items during a Sprint when they are not busy working on the forecast.
D.
The analysts on the Scrum Team document high-ordered Product Backlog items during a Sprint when they are not busy working on the forecast.
Answers
Suggested answer: B

Explanation:

This approach ensures that the Product Backlog items are ready for the Sprint Planning and that the Developers can focus on their work during the Sprint.It also allows the Product Owner to collaborate with the stakeholders and align the Product Backlog with the Product Goal12.The other options are either inefficient, ineffective, or not aligned with the Scrum values and principles


An organization wants to apply Scrum to build a new product and has hired Steven to be the Scrum Master of three new teams that will build the first release. The organization is new to Scrum and asks Steven for advice on how to start. Which two things should Steven first advise? (Choose two.)

A.
Each Scrum Team has its own Product Backlog with items only their team will be working on.
A.
Each Scrum Team has its own Product Backlog with items only their team will be working on.
Answers
B.
One Product Backlog to represent all of the known work needed to be done for the product.
B.
One Product Backlog to represent all of the known work needed to be done for the product.
Answers
C.
Three Product Owners, one for each Scrum Team.
C.
Three Product Owners, one for each Scrum Team.
Answers
D.
Having one Product Owner to be accountable for maximizing the flow of value throughout the development process and provide transparency on the overall progress.
D.
Having one Product Owner to be accountable for maximizing the flow of value throughout the development process and provide transparency on the overall progress.
Answers
Suggested answer: B, D

Explanation:

The Scrum Master serves the organization in several ways, including: Leading and coaching the organization in its Scrum adoption; Planning Scrum implementations within the organization; Helping employees and stakeholders understand and enact Scrum and empirical product development.

Steven is a Scrum Master of a Scrum Team that is new to Scrum. At the halfway point of the Sprint, the Product Owner comes to Steven telling him that he is concerned the Development Team will not be able to complete the entire Sprint Backlog by the end of the Sprint.

What should Steven do in this situation?

A.
Motivate the Development Team to meet their commitment to the Product Owner.
A.
Motivate the Development Team to meet their commitment to the Product Owner.
Answers
B.
Coach the Product Owner that with complex software development, you cannot promise the entire scope that was forecast during Sprint Planning. As more is learned during the Sprint, work may emerge that affects the Sprint Backlog.
B.
Coach the Product Owner that with complex software development, you cannot promise the entire scope that was forecast during Sprint Planning. As more is learned during the Sprint, work may emerge that affects the Sprint Backlog.
Answers
C.
Advise the Product Owner that the Development Team owns the Sprint Backlog and it is up to them to meet their commitments. No one tells the Development Team how to turn Product Backlog into Increments of potentially releasablefunctionality.
C.
Advise the Product Owner that the Development Team owns the Sprint Backlog and it is up to them to meet their commitments. No one tells the Development Team how to turn Product Backlog into Increments of potentially releasablefunctionality.
Answers
D.
Add more people to the Development Team to meet the Product Owner's expectations.
D.
Add more people to the Development Team to meet the Product Owner's expectations.
Answers
Suggested answer: B

Explanation:

Scrum is founded on empirical process control theory, or empiricism. Empiricism asserts that knowledge comes from experience and making decisions based on what is known. The Sprint Backlog is a forecast by the Development Team about what functionality will be in the next Increment and the work needed to deliver that functionality into a 'Done' Increment. The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog emerges during the Sprint. This emergence occurs as the Development Team works through the plan and learns more about the work needed to achieve the Sprint Goal.

Why C is incorrect:

a) The Dev Team does not commit to finishing all items in the Sprint Backlog. Committing to completing all items would be fixed scope and fixed time leaving no room to adapt. They commit to the Sprint Goal and doing the right thing.

b) It's also incorrect for the PO to focus on completing the entire Sprint Backlog. Finishing everything should not be his main focus. Having a shippable increment that meets the Sprint Goal is more important than trying to finish everything.The advice in option C is equivalent to "Don't worry, they'll get everything done." but because of the complex domain, you cannot guarantee everything will get done.

Total 78 questions
Go to page: of 8