A change management review board denied an administrator's request for change. The administrator had provided the purpose and scope of the change, the date and time, and impacted systems with the risk analysis. Which of the following should be included to approve this change?

A.

End-user acceptance

Answers
A.

End-user acceptance

B.

Cost analysis

Answers
B.

Cost analysis

C.

Rollback plan

Answers
C.

Rollback plan

D.

Standard maintenance window

Answers
D.

Standard maintenance window

Suggested answer: C

Explanation:

A rollback plan is essential for a change to be approved by a change management review board. It outlines the steps to reverse a change in case something goes wrong, minimizing downtime and mitigating risk. Other items like end-user acceptance and cost analysis are important but not typically the deciding factor for approval.