What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.

A.

The Finite Scheduling indicator is NOT set in the strategy profile.

Answers
A.

The Finite Scheduling indicator is NOT set in the strategy profile.

B.

The work center has several individual capacities.

Answers
B.

The work center has several individual capacities.

C.

Alternative work centers are fully occupied.

Answers
C.

Alternative work centers are fully occupied.

D.

The Change Planning Direction indicator is set in the strategy profile.

Answers
D.

The Change Planning Direction indicator is set in the strategy profile.

Suggested answer: A, B