Which time elements does MRP consider in backward scheduling to determine the basic dates for components from depender Note: There are 2 correct answers to this question.

A.

Planned delivery time

Answers
A.

Planned delivery time

B.

Total replenishment lead time

Answers
B.

Total replenishment lead time

C.

Operation duration

Answers
C.

Operation duration

D.

Inhouse production time

Answers
D.

Inhouse production time

Suggested answer: A, D