Your project team decides to use a maketoorder planning strategy for a strategic material in discrete manufacturing. What are the impacts of this decision? Note: There are 3 correct answers to this question.

A.

Net requirements calculation is carried out for every sales order individually.

Answers
A.

Net requirements calculation is carried out for every sales order individually.

B.

Production orders are created with sales order reference.

Answers
B.

Production orders are created with sales order reference.

C.

Storage location MRP areas are required for salesorderspecific stock.

Answers
C.

Storage location MRP areas are required for salesorderspecific stock.

D.

Both the reduction of maketoorder stock requirements occur on delivery.

Answers
D.

Both the reduction of maketoorder stock requirements occur on delivery.

E.

Sales orders have to be ATPconfirmed (availabletopromise) to be saved.

Answers
E.

Sales orders have to be ATPconfirmed (availabletopromise) to be saved.

Suggested answer: A, B, E