Question 69 - C_TS422_2023 discussion
You want to set up a maketoorder planning scenario for a finished product. The bill of material contains two components: one should be procured for eac sales order individually the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?
Choose planning strategy 50 (Planning without final assembly) select the corresponding Individual/Collective indicator.
Choose planning strategy 20 (MaketoOrder) select the corresponding Mixed MRP indicator.
Choose planning strategy 50 (Planning without final assembly) select the corresponding Mixed MRP indicator.
Choose planning strategy 20 (MaketoOrder) select the corresponding Individual/Collective indicator.