You want to trigger inhouse production of a semifinished material before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements by dependent requirements for the semifinished material?

A.

Assembly processing with production orders (82)

Answers
A.

Assembly processing with production orders (82)

B.

Planning with final assembly (40)

Answers
B.

Planning with final assembly (40)

C.

Production by lot size (30)

Answers
C.

Production by lot size (30)

D.

Planning at assembly level (70)

Answers
D.

Planning at assembly level (70)

Suggested answer: D