SAP C_TS422_2023 Practice Test - Questions Answers

List of questions

Question 1

Report
Export
Collapse

Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question.

Procurement type

Procurement type

Material type

Material type

MRP type

MRP type

MRP group

MRP group

Suggested answer: A, B
asked 31/10/2024
Chrysovalantis Oikonomopoulos
35 questions

Question 2

Report
Export
Collapse

You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do?

Note: There are 2 correct answers to this question.

Set the creation indicator for purchase requisitions on the initial screen of the MRP run.

Set the creation indicator for purchase requisitions on the initial screen of the MRP run.

Add the agreement to the source list mark it for MRP relevance.

Add the agreement to the source list mark it for MRP relevance.

Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.

Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.

Add the agreement to the quota arrangement mark it for MRP relevance.

Add the agreement to the quota arrangement mark it for MRP relevance.

Suggested answer: B, C
asked 31/10/2024
Jered Anderson
40 questions

Question 3

Report
Export
Collapse

How are dependent requirements for assemblies created? Note: There are 2 correct answers to this question.

They are created together with the independent requirement for the finished product.

They are created together with the independent requirement for the finished product.

They are created on assembly level during the planning run.

They are created on assembly level during the planning run.

They are created with exact times in Advanced Planning.

They are created with exact times in Advanced Planning.

They are only created for multilevel bill of material (BOM) structures.

They are only created for multilevel bill of material (BOM) structures.

Suggested answer: B, C
asked 31/10/2024
Antonio Pombo
36 questions

Question 4

Report
Export
Collapse

Which time elements does MRP consider in backward scheduling to determine the basic dates for components from depender Note: There are 2 correct answers to this question.

Planned delivery time

Planned delivery time

Total replenishment lead time

Total replenishment lead time

Operation duration

Operation duration

Inhouse production time

Inhouse production time

Suggested answer: A, D
asked 31/10/2024
Rio Ordonez
40 questions

Question 5

Report
Export
Collapse

What determines whether the planned independent requirements in dem management are consumed by other requirements? Note: There are 2 correct answers to this question.

Order type

Order type

Requirements profile

Requirements profile

Requirements type

Requirements type

Planning strategy

Planning strategy

Suggested answer: C, D
asked 31/10/2024
Miguel Villanueva
33 questions

Question 6

Report
Export
Collapse

What does forecasting in the dem planning cycle include? Note: There are 3 correct answers to this question.

Oneoff events

Oneoff events

Past production planning quantities

Past production planning quantities

Past quotation quantities

Past quotation quantities

Market intelligence

Market intelligence

Past sales order quantities

Past sales order quantities

Suggested answer: A, D, E
asked 31/10/2024
IQBAL SHAIKH
34 questions

Question 7

Report
Export
Collapse

Which SAP applications can be used for forecasting in Supply Chain Planning? Note: There are 2 correct answers to this question.

Integrated Business Planning (IBP)

Integrated Business Planning (IBP)

Supply Chain Management (SCM)

Supply Chain Management (SCM)

Material Requirements Planning (MRP)

Material Requirements Planning (MRP)

Capacity Requirements Planning (CRP)

Capacity Requirements Planning (CRP)

Suggested answer: A, B
asked 31/10/2024
Tolga Kesici
48 questions

Question 8

Report
Export
Collapse

What will happen in the MRP run if you have created a new MRPrelevant material that supports both inhouse production external procurement?

The MRP run assumes external procurement.

The MRP run assumes external procurement.

The MRP run assumes inhouse production.

The MRP run assumes inhouse production.

The MRP run plans the material only if a quotation has been maintained.

The MRP run plans the material only if a quotation has been maintained.

The MRP run does NOT consider the material; it has to be planned interactively.

The MRP run does NOT consider the material; it has to be planned interactively.

Suggested answer: B
asked 31/10/2024
javier mungaray
34 questions

Question 9

Report
Export
Collapse

Where does the system check master data selection settings during the creation of planned orders production orders? Note: There are 3 correct answers to this question.

In the production version

In the production version

In the work centers

In the work centers

In the bill of material (BOM)

In the bill of material (BOM)

In the MRP controller

In the MRP controller

In the routing

In the routing

Suggested answer: C, D, E
asked 31/10/2024
Domenico D'Angelo
40 questions

Question 10

Report
Export
Collapse

During production order creation several valid production versions are found. How does the system choose the production version?

Alphanumeric or quota arrangement

Alphanumeric or quota arrangement

Planned order or material number

Planned order or material number

Validity period or sales order

Validity period or sales order

Lot size or material cost

Lot size or material cost

Suggested answer: A
asked 31/10/2024
ERIK BURDETT
42 questions
Total 79 questions