Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question.
Procurement type
Material type
MRP type
MRP group
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do?
Note: There are 2 correct answers to this question.
Set the creation indicator for purchase requisitions on the initial screen of the MRP run.
Add the agreement to the source list mark it for MRP relevance.
Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
Add the agreement to the quota arrangement mark it for MRP relevance.
How are dependent requirements for assemblies created? Note: There are 2 correct answers to this question.
They are created together with the independent requirement for the finished product.
They are created on assembly level during the planning run.
They are created with exact times in Advanced Planning.
They are only created for multilevel bill of material (BOM) structures.
Which time elements does MRP consider in backward scheduling to determine the basic dates for components from depender Note: There are 2 correct answers to this question.
Planned delivery time
Total replenishment lead time
Operation duration
Inhouse production time
What determines whether the planned independent requirements in dem management are consumed by other requirements? Note: There are 2 correct answers to this question.
Order type
Requirements profile
Requirements type
Planning strategy
What does forecasting in the dem planning cycle include? Note: There are 3 correct answers to this question.
Oneoff events
Past production planning quantities
Past quotation quantities
Market intelligence
Past sales order quantities
Which SAP applications can be used for forecasting in Supply Chain Planning? Note: There are 2 correct answers to this question.
Integrated Business Planning (IBP)
Supply Chain Management (SCM)
Material Requirements Planning (MRP)
Capacity Requirements Planning (CRP)
What will happen in the MRP run if you have created a new MRPrelevant material that supports both inhouse production external procurement?
The MRP run assumes external procurement.
The MRP run assumes inhouse production.
The MRP run plans the material only if a quotation has been maintained.
The MRP run does NOT consider the material; it has to be planned interactively.
Where does the system check master data selection settings during the creation of planned orders production orders? Note: There are 3 correct answers to this question.
In the production version
In the work centers
In the bill of material (BOM)
In the MRP controller
In the routing
During production order creation several valid production versions are found. How does the system choose the production version?
Alphanumeric or quota arrangement
Planned order or material number
Validity period or sales order
Lot size or material cost