Question 41

Why do you use Engineering Change Management? Note: There are 2 correct answers to this question.
To monitor document table changes
To enable integration into a sales order
To save multiple changes for an object
To monitor document object changes
Question 42

Which of the following processes lead to an entry in the MRP planning file? Note: There are 2 correct answers to this question.
Changing the delivery address in transportation management
Changing the storage bin in warehouse management
Changing the procurement type in the product master
Changing the stock in inventory management
Question 43

What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.
Planned order
Scheduling agreement schedule line
Production order
Purchase order
Question 44

Advanced Planning uses master data from SAP S/4HANA Cloud Private Edition. In which data objects can you set the Advanced Planning flag? Note: There are 2 correct answers to this question.
Work center
Plant
Production version
Material
Question 45

What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation? Note: There are 2 correct answers to this question.
Scheduling of an operation takes place as close as possible to the desired date.
Sequencing on multiactivity resources is automatically updated.
Neighboring operations can be moved in both directions in order to create a slot.
Changes are automatically implemented in the complete collective order.
Question 46

Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.
Assign the alert profile to the overall profile.
Assign the overall profile to the authorization profile.
Create an object selection variant for alerts according to the priority of ATP categories.
Create an object selection variant for productionplanningrelated alerts.
Question 47

How would you define pegging in the context of Advanced Planning?
Question 48

What can you use stard heuristics in Advanced Planning (PP/DS) for?
Question 49

Your production planners are allowed to execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?
Question 50

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.