Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?
When several operations are maintained for one product
When alternative resources are used within one operation
When several production versions are maintained for one product
When multiple planned orders are scheduled in parallel on one resource
You use planning strategy Finite Scheduling with Reverse want to allow scheduling in the past. How can you parameterize this in the strategy profile?
Specify a negative offset time.
Specify a negative opening period.
Specify a negative planning horizon.
Specify a negative PP/DS horizon.
You are a consultant on an SAP S/4HANA Cloud brownfield project. In a meeting the customer decides to remodel an existing business process in accordance with clean core principles.
Which of the following SAP Signavio solutions can be used for the remodeling?
SAP Signavio Process Insights
SAP Signavio Process Intelligence
SAP Signavio Process Governance
SAP Signavio Process Manager
You are a consultant on an SAP S/4HANA Cloud Greenfield project.
Which of the following aspects should you focus on to achieve maintain clean core data quality? Note: There are 2 correct answers to this question.
Efficiency
Accuracy
Timeliness
Stability
What are some SAP recommended guiding principles to achieve clean core operations? Note: There are 3 correct answers to this question.
Establish an organizational structure technical foundation transformation methodology for clean core.
Integrate clean core practices in the endtoend value process chain.
Establish release management.
Establish regular housekeeping tasks procedures.
Define roles responsibilities as part of a process transformation office.
Which of the following are features of the clean core dashboard? Note: There are 2 correct answers to this question.
Customers can grant access to the dashboard to partners.
Customers can use the dashboard in the dev test production tenants.
It can be accessed by using SAP For Me.
It can be used in all SAP S/4HANA Cloud editions.
What options does a planner have in the planning table for repetitive manufacturing? Note: There are 2 correct answers to this question.
Change the assignments of production quantities to production lines.
Create new production quantities.
Dispatch operations to work centers.
Reschedule deallocate operations.
Where do you maintain the work center that represents the production line for repetitive manufacturing? Note: There are 2 correct answers to this question.
Production cost collector
Production version
Repetitive manufacturing profile
Routing
What are the prerequisites for a reporting point confirmation in repetitive manufacturing? Note: There are 2 correct answers to this question.
Activating the reporting point backflush in the order dependent parameters
Activating the reporting point backflush in the work centers
Defining the relevant work centers in the routing
Defining the operations as reporting points using the control key
Which options do you have to plan both quantities capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.
Assign planned orders manually in the planning table.
Run MRP with quota arrangement.
Run MRP with automatic selection of production version.
Run PP/DS heuristics for repetitive manufacturing.