SAP C_TS422_2023 Practice Test - Questions Answers, Page 2
List of questions
Related questions
How can a material availability check be triggered automatically for a production order? Note: There are 2 correct answers to this question.
By capacity planning
By order confirmation
By order release
By mass processing
For a production version to be valid consistent what requirements must be fulfilled? Note: There are 3 correct answers to this question.
The deletion flag must NOT be set for the bill of material (BOM) or the routing.
The consistency check must be performed.
The assigned routing bill of material (BOM) must be valid in the entire validity period.
The assigned routing bill of material (BOM) must have the same validity period.
The lot size range must be within the lot size range of the assigned routing.
You want to use capacity availability checks for production orders. Which settings have to be made for this?
Note: There are 2 correct answers to this question.
The Relevant for Finite Scheduling indicator must be set.
The scope of check must be defined in Customizing.
A checking rule must be assigned to the work centers.
An overall profile must be assigned in the checking control.
Which business processes are affected by settings in the order type dependent parameters? Note: There are 2 correct answers to this question.
Schedule production orders.
Check material availability.
Select master data.
Define integration with cost accounting.
For production orders cost object controlling (COC) can be carried out on an order related or product related basis. Which of the following do you have to consider?
Note: There are 2 correct answers to this question.
Productrelated COC is used in manufacturing for coproducts.
In productrelated COC all costs are debited credited to a product cost collector.
In orderrelated COC individual production orders do NOT have cost segments.
Orderrelated COC is beneficial in a flexible production environment.
Which of the following automation options can you use for production orders? Note: There are 2 correct answers to this question.
You can use trigger points to automatically create rework orders via confirmations.
You can use mass processing to set production orders to technically complete.
You can use the production scheduling profile to automatically set orders to technically complete.
You can use mass processing to read PP master data for production orders.
You want to create a production order. What methods can you use?
Note: There are 2 correct answers to this question.
Convert a purchase requisition
Create without material
Create by order release
Create in Kanban process
What are the advantages of collective orders? Note: There are 2 correct answers to this question.
To perform availability checks across the entire collective order
To coordinate orders in the planning board for a collective order
To show the flow of batches across the entire collective order
To post confirmations for the entire collective order
What is a prerequisite for consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?
MRP creates a dependent requirement.
A sales order is delivered.
MRP creates a planned order.
A sales order is created.
Where do you maintain data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.
Work center
Material master
Routing
Production version