Question 9 - C_TS422_2023 discussion
Where does the system check master data selection settings during the creation of planned orders production orders? Note: There are 3 correct answers to this question.
A.
In the production version
B.
In the work centers
C.
In the bill of material (BOM)
D.
In the MRP controller
E.
In the routing