What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.
A.
You can reschedule the operation using lead time scheduling.
B.
You can reschedule the operation using infinite scheduling in a planning table.
C.
You can reschedule the operation using finite scheduling in a planning table.
D.
You can reschedule the operation in the Manage Work Center Capacity app.