What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.

A.

You can reschedule the operation using lead time scheduling.

Answers
A.

You can reschedule the operation using lead time scheduling.

B.

You can reschedule the operation using infinite scheduling in a planning table.

Answers
B.

You can reschedule the operation using infinite scheduling in a planning table.

C.

You can reschedule the operation using finite scheduling in a planning table.

Answers
C.

You can reschedule the operation using finite scheduling in a planning table.

D.

You can reschedule the operation in the Manage Work Center Capacity app.

Answers
D.

You can reschedule the operation in the Manage Work Center Capacity app.

Suggested answer: C, D