Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?

A.

Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity

Answers
A.

Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity

B.

Relative effort estimate in Ideal Person Days that reflects the best estimate by the Project Team

Answers
B.

Relative effort estimate in Ideal Person Days that reflects the best estimate by the Project Team

C.

Product Owner's relative effort estimate that will be needed to implement and test the user story

Answers
C.

Product Owner's relative effort estimate that will be needed to implement and test the user story

D.

Detailed bottom-up effort estimate by the Product Owner that breaks up each story into short tasks

Answers
D.

Detailed bottom-up effort estimate by the Product Owner that breaks up each story into short tasks

Suggested answer: A

Explanation:

In Agile practices within SAP Activate, estimation is often conducted using 'story points' to evaluate relative size and complexity. A top-down approach led by the Scrum Master ensures that all aspects of story complexity are considered, facilitating accurate, consensus-driven estimates.