Which activity helps the project team identify and add user stories to the backlog?

A.

Assessing documentation requirements

Answers
A.

Assessing documentation requirements

B.

Benchmarking current business processes

Answers
B.

Benchmarking current business processes

C.

Planning the release and sprints

Answers
C.

Planning the release and sprints

D.

Conducting the fit-to-standard workshop

Answers
D.

Conducting the fit-to-standard workshop

Suggested answer: D

Explanation:

The fit-to-standard workshop is a key activity in SAP Activate that involves aligning SAP standard processes with business requirements. During this workshop, the team identifies gaps and additional requirements, which are then translated into user stories and added to the backlog for implementation.