Question 1
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which of the following activities take place during the Discover phase in an SAP BW/4HANA implementation? Note: There are 2 correct answers to this question.
Create, review, and sign off the Project Charter.
Discuss the benefits and functionality of SAP Analytics Cloud.
Create, review, and sign off the Project Management Plan.
Discuss the benefits of SAP Data Warehouse Cloud.
Explanation:
In the Discover phase of an SAP BW/4HANA implementation, high-level discussions on the benefits of related tools like SAP Analytics Cloud and SAP Data Warehouse Cloud take place. This phase focuses on exploring and understanding available functionalities to inform decision-making.
Question 2
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
When conducting an upgrade of an SAP S/4HANA Cloud, public edition three-system landscape, in which phase are the Business Roles updated?
Explore
Deploy
Discover
Realize
Explanation:
During the Realize phase, Business Roles are updated to align with the upgraded solution's requirements and configurations. This ensures that the roles meet both security and functional needs in the updated environment.
Question 3
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
You are transitioning to SAP S/4HAN
In which phase do you adjust custom code?
Realize
Deploy
Explore
Prepare
Explanation:
Custom code adjustments are typically made in the Realize phase, where the system configuration and development activities take place. This phase involves adapting custom code to align with SAP S/4HANA's updated architecture and functionalities.
Question 4
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
In which phase do you collect the main functional attributes of the product as per the Agile definition?
Discover
Prepare
Explore
Realize
Explanation:
In SAP Activate's Agile Project Planning, the Explore phase is when teams refine and capture the main functional attributes of the product, often through user stories and requirements workshops. This phase allows teams to iteratively understand, document, and confirm the main attributes before moving to realization.
Question 5
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
What information does the project team need before they can correctly estimate the relative size of backlog user stories? Note: There are 2 correct answers to this question.
Available project resources
Definition of Ready
Definition of Done
Benchmark user story
Explanation:
The 'Definition of Ready' (DoR) ensures that user stories meet predefined criteria before estimation, while the 'Definition of Done' (DoD) clarifies the completion standards. Both definitions support accurate estimations by establishing clear, mutual expectations for user stories.
Question 6
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?
Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity
Relative effort estimate in Ideal Person Days that reflects the best estimate by the Project Team
Product Owner's relative effort estimate that will be needed to implement and test the user story
Detailed bottom-up effort estimate by the Product Owner that breaks up each story into short tasks
Explanation:
In Agile practices within SAP Activate, estimation is often conducted using 'story points' to evaluate relative size and complexity. A top-down approach led by the Scrum Master ensures that all aspects of story complexity are considered, facilitating accurate, consensus-driven estimates.
Question 7
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
What is Scrum of Scrums?
Inspection of code and configuration prior to sprint demo
Integration meeting among the various Scrum teams
Scrum team led by very experienced Scrum master
Alternative to regular Scrum process for a very large team
Explanation:
The Scrum of Scrums is a cross-team coordination meeting, allowing teams working on interconnected deliverables to synchronize efforts, address dependencies, and manage impediments. This approach is beneficial for large projects requiring multiple Scrum teams.
Question 8
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
What are the responsibilities of the product owner in release and sprint planning? Note: There are 2 correct answers to this question.
Estimate the backlog user stories.
Define objectives for each release.
Analyze the functional and technical dependencies between user stories.
Prioritize backlog user stories by business priority.
Explanation:
The product owner's responsibilities include defining objectives for each release to align with business goals and prioritizing backlog items by business priority to ensure high-value deliverables are completed first. While the team estimates user stories, the product owner ensures clarity and prioritization.
Question 9
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which activity helps the project team identify and add user stories to the backlog?
Assessing documentation requirements
Benchmarking current business processes
Planning the release and sprints
Conducting the fit-to-standard workshop
Explanation:
The fit-to-standard workshop is a key activity in SAP Activate that involves aligning SAP standard processes with business requirements. During this workshop, the team identifies gaps and additional requirements, which are then translated into user stories and added to the backlog for implementation.
Question 10
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?
Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.
Realize phase scope, planning, and budget should be completed and final.
User stories on the product backlog should be in a ready state for the first 2 to 3 sprints.
Release plan and sprint ceremony guidelines should be finalized.
Explanation:
At the start of the Realize phase, basic sprint planning and duration for the first few sprints should be established to ensure a smooth start. This approach supports incremental development by setting priorities and defining the immediate tasks for the project team.
Question