When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?

A.

Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.

Answers
A.

Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.

B.

Realize phase scope, planning, and budget should be completed and final.

Answers
B.

Realize phase scope, planning, and budget should be completed and final.

C.

User stories on the product backlog should be in a ready state for the first 2 to 3 sprints.

Answers
C.

User stories on the product backlog should be in a ready state for the first 2 to 3 sprints.

D.

Release plan and sprint ceremony guidelines should be finalized.

Answers
D.

Release plan and sprint ceremony guidelines should be finalized.

Suggested answer: A

Explanation:

At the start of the Realize phase, basic sprint planning and duration for the first few sprints should be established to ensure a smooth start. This approach supports incremental development by setting priorities and defining the immediate tasks for the project team.