Question 10 - C_ACT_2403 discussion
When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?
A.
Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.
B.
Realize phase scope, planning, and budget should be completed and final.
C.
User stories on the product backlog should be in a ready state for the first 2 to 3 sprints.
D.
Release plan and sprint ceremony guidelines should be finalized.