What are the responsibilities of the product owner in release and sprint planning? Note: There are 2 correct answers to this question.
A.
Estimate the backlog user stories.
B.
Define objectives for each release.
C.
Analyze the functional and technical dependencies between user stories.
D.
Prioritize backlog user stories by business priority.