What activity do you perform during the daily stand-up meeting?

A.

Refine acceptance criteria for the sprint.

Answers
A.

Refine acceptance criteria for the sprint.

B.

Re-baseline the release plan.

Answers
B.

Re-baseline the release plan.

C.

Demo completed features.

Answers
C.

Demo completed features.

D.

Report showstoppers.

Answers
D.

Report showstoppers.

Suggested answer: D

Explanation:

The daily stand-up meeting is focused on team alignment, with members reporting any roadblocks (or 'showstoppers') that hinder their progress. This activity ensures timely identification and resolution of issues affecting sprint goals.