ExamGecko
Question list
Search
Search

Question 23 - C_ACT_2403 discussion

Report
Export

Who determines the tasks that are required to complete the committed backlog items in a Sprint?

A.

Project manager

Answers
A.

Project manager

B.

Scrum master

Answers
B.

Scrum master

C.

Scrum team

Answers
C.

Scrum team

D.

Product owner

Answers
D.

Product owner

Suggested answer: C

Explanation:

In Agile methodology, the Scrum team self-organizes to determine the specific tasks needed to complete backlog items. This autonomy encourages accountability and collaboration among team members to achieve sprint goals.

asked 19/11/2024
Kareem Dadoul
43 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first