When does the Scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?

A.

During the sprint review

Answers
A.

During the sprint review

B.

During the sprint retrospective

Answers
B.

During the sprint retrospective

C.

During the sprint backlog review

Answers
C.

During the sprint backlog review

D.

During the sprint user acceptance test

Answers
D.

During the sprint user acceptance test

Suggested answer: A

Explanation:

In Agile project delivery, the sprint review is the formal event where the Scrum team demonstrates the completed user stories to the product owner and stakeholders. This is when the product owner confirms whether each user story meets the acceptance criteria and is considered complete.