ExamGecko
Home / SAP / C_ACT_2403 / List of questions
Ask Question

SAP C_ACT_2403 Practice Test - Questions Answers, Page 3

List of questions

Question 21

Report
Export
Collapse

What activity do you perform during the daily stand-up meeting?

Refine acceptance criteria for the sprint.

Refine acceptance criteria for the sprint.

Re-baseline the release plan.

Re-baseline the release plan.

Demo completed features.

Demo completed features.

Report showstoppers.

Report showstoppers.

Suggested answer: D

Explanation:

The daily stand-up meeting is focused on team alignment, with members reporting any roadblocks (or 'showstoppers') that hinder their progress. This activity ensures timely identification and resolution of issues affecting sprint goals.

asked 19/11/2024
Nicolas Da Silva
42 questions

Question 22

Report
Export
Collapse

What criteria does the product owner use to sequence the backlog? Note: There are 2 correct answers to this question.

Technical dependencies

Technical dependencies

Duration of the sprint

Duration of the sprint

Complexity of the story

Complexity of the story

Business priority

Business priority

Suggested answer: A, D

Explanation:

The product owner sequences backlog items primarily based on business priority to deliver the highest value first, while also considering technical dependencies to prevent development delays. This approach optimizes the team's efficiency in delivering value.

asked 19/11/2024
M S
30 questions

Question 23

Report
Export
Collapse

Who determines the tasks that are required to complete the committed backlog items in a Sprint?

Project manager

Project manager

Scrum master

Scrum master

Scrum team

Scrum team

Product owner

Product owner

Suggested answer: C

Explanation:

In Agile methodology, the Scrum team self-organizes to determine the specific tasks needed to complete backlog items. This autonomy encourages accountability and collaboration among team members to achieve sprint goals.

asked 19/11/2024
Kareem Dadoul
43 questions

Question 24

Report
Export
Collapse

What is the purpose of the scrum board?

To show readiness of the release

To show readiness of the release

To visualize the resource load

To visualize the resource load

To visualize team progress

To visualize team progress

To document the results of the fit-to-standard workshop

To document the results of the fit-to-standard workshop

Suggested answer: C

Explanation:

The scrum board is used to visually track team progress on sprint tasks. By displaying each task's current status, it provides transparency, helping team members and stakeholders stay updated on the sprint's progress.

asked 19/11/2024
luigi catalano
37 questions

Question 25

Report
Export
Collapse

When does the Scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?

During the sprint review

During the sprint review

During the sprint retrospective

During the sprint retrospective

During the sprint backlog review

During the sprint backlog review

During the sprint user acceptance test

During the sprint user acceptance test

Suggested answer: A

Explanation:

In Agile project delivery, the sprint review is the formal event where the Scrum team demonstrates the completed user stories to the product owner and stakeholders. This is when the product owner confirms whether each user story meets the acceptance criteria and is considered complete.

asked 19/11/2024
Martin Lundgren
39 questions

Question 26

Report
Export
Collapse

What is the objective of using scaling Scrum techniques when coordinating large teams in complex projects?

To reallocate staff to skill-based teams such as developers in one single team.

To reallocate staff to skill-based teams such as developers in one single team.

To bring all specialists, such as the company legal advisors, into the Scrum team.

To bring all specialists, such as the company legal advisors, into the Scrum team.

To manage the flow of information between the project and stakeholders.

To manage the flow of information between the project and stakeholders.

To ensure alignment in architecture, configuration, and integration.

To ensure alignment in architecture, configuration, and integration.

Suggested answer: D

Explanation:

Scaling Scrum techniques, like Scrum of Scrums, aim to ensure consistent alignment in architecture, configuration, and integration across multiple teams. This approach helps large projects maintain a cohesive structure and unified progress, especially in complex implementations.

asked 19/11/2024
Ernest Altagracia Marte
40 questions

Question 27

Report
Export
Collapse

How do you set up Scrum teams? Note: There are 2 correct answers to this question.

As a cross-functional team covering multiple functions, like configuration, data loads, and testing.

As a cross-functional team covering multiple functions, like configuration, data loads, and testing.

By type of work, like configuration Scrum, documentation Scrum, and testing Scrum.

By type of work, like configuration Scrum, documentation Scrum, and testing Scrum.

Based on group size, but a minimum of 12 people.

Based on group size, but a minimum of 12 people.

Based on end-to-end processes like order-to-cash.

Based on end-to-end processes like order-to-cash.

Suggested answer: A, D

Explanation:

Scrum teams are often set up as cross-functional teams with a mix of expertise (e.g., configuration, data loads) or based on end-to-end processes (like order-to-cash). These setups allow teams to work collaboratively across different aspects of the project while focusing on functional flows.

asked 19/11/2024
Ehsan Ali
40 questions

Question 28

Report
Export
Collapse

According to the Definition of Done, which activity must be completed for each Sprint?

Configuration must be transported to the production system.

Configuration must be transported to the production system.

Functionality must be released to the business.

Functionality must be released to the business.

Refinement of user story description must be completed.

Refinement of user story description must be completed.

The solution must be built and configured in the development system.

The solution must be built and configured in the development system.

Suggested answer: D

Explanation:

The Definition of Done specifies that all work for a sprint must be completed in the development system to ensure that each increment is ready for potential release. This includes configuration, testing, and documentation, preparing the solution for further testing and deployment.

asked 19/11/2024
EDDIE LIN
43 questions

Question 29

Report
Export
Collapse

What do you do during the sprint retrospective meeting?

Define sprint activities and best practices with the customer.

Define sprint activities and best practices with the customer.

Plan future sprints with the customer.

Plan future sprints with the customer.

Discuss best practices with the Scrum Team.

Discuss best practices with the Scrum Team.

Document best practices guided by the Scrum Master.

Document best practices guided by the Scrum Master.

Suggested answer: D

Explanation:

During the sprint retrospective, the Scrum Master guides the team in reflecting on the sprint's successes and challenges. Best practices and lessons learned are documented to improve future sprints, fostering continuous improvement.

asked 19/11/2024
sheldan simeina
36 questions

Question 30

Report
Export
Collapse

Which of the following is a key characteristic of the Agile project approach?

Higher business involvement in the early phases

Higher business involvement in the early phases

Frequent and detailed release scheduling

Frequent and detailed release scheduling

Iterative build with frequent inspections

Iterative build with frequent inspections

Frequent quality gates in each sprint

Frequent quality gates in each sprint

Suggested answer: C

Explanation:

A core feature of Agile is its iterative nature, with regular inspections throughout each sprint. This approach ensures adaptability and early issue resolution, promoting continuous alignment with business requirements.

asked 19/11/2024
Eddie Martinez
36 questions
Total 80 questions
Go to page: of 8