Question 35 - C_ACT_2403 discussion
What is the correct phase order of an SAP Activate project?
A.
Prepare > Explore > Discover > Realize > Deploy
B.
Prepare > Discover > Explore > Realize > Deploy > Run
C.
Prepare > Explore > Realize > Deploy > Run
D.
Prepare > Explore > Realize > Deploy > Run