What is the correct phase order of an SAP Activate project?

A.

Prepare > Explore > Discover > Realize > Deploy

Answers
A.

Prepare > Explore > Discover > Realize > Deploy

B.

Prepare > Discover > Explore > Realize > Deploy > Run

Answers
B.

Prepare > Discover > Explore > Realize > Deploy > Run

C.

Prepare > Explore > Realize > Deploy > Run

Answers
C.

Prepare > Explore > Realize > Deploy > Run

D.

Prepare > Explore > Realize > Deploy > Run

Answers
D.

Prepare > Explore > Realize > Deploy > Run

Suggested answer: C

Explanation:

The correct phase order in the SAP Activate methodology for an SAP project is Prepare > Explore > Realize > Deploy > Run. This sequence represents the structured progression from project setup to solution deployment and operations.