Which of the following best outlines the sequence of testing in the Realize phase?

A.

Data Migration String Test User Acceptance Test

Answers
A.

Data Migration String Test User Acceptance Test

B.

String Test Integration Test User Acceptance Test

Answers
B.

String Test Integration Test User Acceptance Test

C.

String Test User Acceptance Test Integration Test

Answers
C.

String Test User Acceptance Test Integration Test

D.

Integration Test User Acceptance Test String Test

Answers
D.

Integration Test User Acceptance Test String Test

Suggested answer: B

Explanation:

The typical sequence of testing in the Realize phase begins with the String Test, followed by the Integration Test to validate cross-functional flows, and concludes with the User Acceptance Test (UAT) to confirm system readiness from an end-user perspective.