You manage a Scrum project with two development teams.

Issues are associated with each team using a custom field called Jean.

Parallel sprints have been disabled.

Which setup will provide each team with an individual Burndown Chart?

A.
a single Scrum board with quick filters
Answers
A.
a single Scrum board with quick filters
B.
a single Scrum board using the Team field as the Estimation Statistic
Answers
B.
a single Scrum board using the Team field as the Estimation Statistic
C.
two Scrum boards using the Team field as the Estimation Statistic
Answers
C.
two Scrum boards using the Team field as the Estimation Statistic
D.
two Scrum boards using the Team field in their board filters
Answers
D.
two Scrum boards using the Team field in their board filters
Suggested answer: D

Explanation:

If you manage a Scrum project with two development teams and want to provide each team with an individual Burndown Chart, you can create two Scrum boards using the Team field in their board filters. A Burndown Chart is a report that shows the amount of work remaining in a sprint, based on the issues that are included in the board filter. By using the Team field in the board filter, you can ensure that each board only shows the issues that belong to a specific team, and thus generate a separate Burndown Chart for each team. The other options will either show a combined Burndown Chart for both teams or not use the Team field at all. Therefore, the correct answer is D.Reference: [Creating a board], [Configuring filters], [Viewing the Burndown Chart]