Question 5 - ACP-610 discussion
Your team uses Story Points for estimation and tracking.
You performed several actions in the active sprint.
Which two actions are reflected as scope change? (Choose two.)
A.
Added a fix version on a committed story.
B.
Estimated a story in the backlog.
C.
Dragged on estimated story from the backlog to the sprint.
D.
Modified the estimate value on a committed story.
E.
Added another 5ub-task to a committed story.
F.
Logged work on several committed stories.