The release manager is requesting a list of all issues included in a particular sprint. Which report will provide this information?

A.
Control Chart
Answers
A.
Control Chart
B.
Release Burndown
Answers
B.
Release Burndown
C.
Version Report
Answers
C.
Version Report
D.
Sprint Report
Answers
D.
Sprint Report
E.
Average Age Report
Answers
E.
Average Age Report
Suggested answer: D

Explanation:

A Sprint Report is the best report to provide a list of all issues included in a particular sprint. A Sprint Report shows the scope, status, and completion date of each sprint. It also displays a breakdown of the completed, incomplete, and added issues in the sprint. The release manager can easily view the list of incomplete issues in the Issue Navigator by clicking on the View in Issue Navigator link at the bottom of the report. A Sprint Report also helps to track the team's performance and identify any scope changes during the sprint.Reference:Managing Jira Projects Data Center and Server: Certification Bundle, [Sprint Report | Jira Software Cloud]