Question 28 - ACP-610 discussion
Sam and Jo are product managers responsible for two separate products. Each product has its own Jira project and a corresponding Scrum board.
Management requests an integration between the products. Sam and Jo decide to create all the integration-related issues in Sams project and label them integration'.
Jo updated his Scrum board's saved filter to include the relevant integration issues from Sam's project.
Which statement is definitely true?
A.
All integration issues always appear on top of Jo's backlog.
B.
Changes to the rank of integration issues on Jo's board are reflected on Sam's board.
C.
Jo is unable to rank integration issues created by Sam.
D.
Sam is unable to transition integration issues that were ranked by Jo.
E.
Integration issues can only be ranked on Sam's board.