Question 41 - ACP-610 discussion
You just started working as a scrum master in the Engine team.
The first thing you do is to analyze the Velocity Chart of the team's scrum board as shown
A.
Issues not completed in Combo Sprint 3 were completed in Combo Sprint 4.
B.
Combo Sprint 1 has been deleted after it was completed.
C.
There was a scope change during Combo Sprint 4.
D.
The team only completed 2 out of 6 Story Points in Combo Sprint 3.
E.
All issues in Combo Sprint 3 were estimated before the sprint was started.
Your answer: